Component Readiness

18 components short and 82 sub-assemblies late across 54 machines
AB Archie Production Manager
Shortages and actions Forward requirements Stock, ordersNetting, dates
Decisions already late
10

Of 18 shortages, 10 passed the day the order had to be placed. The action date is the day it is needed minus the lead time, and it is not a warning — it is arithmetic.

Biggest single exposure
HY-VB-WV-AB Walvoil ActiveBlock proportional module

Short on 20 machines. First needed 19 Oct 2026; the order had to be placed by 13 Jul 2026, which was 57 days ago. Cover lands 3 Nov 2026 on PO-26-381, which is 15 days after it is needed. Lead time is 98 days from Walvoil S.p.A..

Everything that will not be ready in time

72 rows, soonest first
Item Needed for Required Available Short Needed by Lead Action by Cover Action
5 sub-assemblies late
Hydraulic pack, standard, Valve bank assembly, Walvoil SD5 6-bank, Ram set, medium mast, Hose kit, medium mast, Decal and document set, KH
BO-26-4107
Series 3 / PB650 / Hinge Adapter + RSE Turner · NC Equipment Ltd
5 — 5 26 Aug 2d 8 Sep Worst is Hydraulic pack, standard, ready 9 Sep, 10 days late Shop floor
1 sub-assembly late
Decal and document set, MX
BO-26-4113
Multi-Cut 2100 / Mounted · Whanganui Machinery Centre Ltd
1 — 1 28 Aug 1d 8 Sep Worst is Decal and document set, MX, ready 8 Sep, 7 days late Shop floor
5 sub-assemblies late
Hydraulic pack, ActiveBlock, Valve bank assembly, Walvoil ActiveBlock, Ram set, large mast, Hose kit, large mast, Decal and document set, FP
BO-26-4115
Ultra G4 / RB800 · Otago Farm Machinery Ltd
5 — 5 31 Aug 2d 8 Sep Worst is Hydraulic pack, ActiveBlock, ready 9 Sep, 7 days late Shop floor
5 sub-assemblies late
Hydraulic pack, standard, Valve bank assembly, Walvoil SD5 4-bank, Ram set, medium mast, Hose kit, medium mast, Decal and document set, FP
BO-26-4117
Mule / SM900 / Hinge Adapter · Pilbara Fencing Pty Ltd
5 — 5 31 Aug 2d 8 Sep Worst is Hydraulic pack, standard, ready 8 Sep, 6 days late Shop floor
8 sub-assemblies late
Mule mast weldment, UltraGlide RS base weldment, Rock Spike Extractor Kit, Hydraulic pack, standard, Valve bank assembly, Walvoil SD5 4-bank, Ram set, medium mast, Hose kit, medium mast, Decal and document set, FP
BO-26-4111
Mule / UltraGlide / Rock Spike · QuikFence Australia Pty Ltd
8 — 8 2 Sep 6d 15 Sep Worst is Mule mast weldment, ready 22 Sep, 14 days late
waiting on ST-IB350-200UB
Shop floor
7 sub-assemblies late
Kinghitter Series 2 mast weldment, Digger Hitch base weldment, Hydraulic pack, standard, Valve bank assembly, Walvoil SD5 4-bank, Ram set, medium mast, Hose kit, medium mast, Decal and document set, KH
BO-26-4130
Series 2 / Digger · Giltrap AgriZone Ltd
7 — 7 4 Sep 6d 15 Sep Worst is Kinghitter Series 2 mast weldment, ready 22 Sep, 12 days late
waiting on ST-IB350-200UB
Shop floor
ST-IB350-200UB
Infrabuild 350 I-beam 200UB22, mill run
13 machines
65.4 0 65.4 8 Sep 70d 30 Jun
70 days late
PO-26-383 · 15 Sep
7 days late
1 sub-assembly late
Hydraulic pack, standard
BO-26-4126
Series 3 / SM900 · Delmade Pty Ltd
1 — 1 8 Sep 2d 8 Sep Worst is Hydraulic pack, standard, ready 9 Sep, 1 day late Shop floor
1 sub-assembly late
Mule mast weldment
BO-26-4133
Mule / SM900 · Webbline Agriculture Ltd
1 — 1 14 Sep 6d 15 Sep Worst is Mule mast weldment, ready 18 Sep, 4 days late
waiting on ST-IB350-200UB
Shop floor
1 sub-assembly late
Mule mast weldment
BO-26-4134
Mule / SM1000 · Waikato Fencing Systems Ltd
1 — 1 14 Sep 6d 15 Sep Worst is Mule mast weldment, ready 18 Sep, 4 days late
waiting on ST-IB350-200UB
Shop floor
1 sub-assembly late
Kinghitter Series 2 mast weldment
BO-26-4135
Series 2 / PB650 · Giltrap AgriZone Ltd
1 — 1 14 Sep 6d 15 Sep Worst is Kinghitter Series 2 mast weldment, ready 16 Sep, 2 days late
waiting on ST-IB350-200UB
Shop floor
1 sub-assembly late
Mule mast weldment
BO-26-4139
Mule / PB650 / Reversible SM Linkage · Otago Farm Machinery Ltd
1 — 1 15 Sep 6d 15 Sep Worst is Mule mast weldment, ready 21 Sep, 4 days late
waiting on ST-IB350-200UB
Shop floor
1 sub-assembly late
Mule-V mast weldment
BO-26-4138
Mule-V / MS350 · Gippsland Fencing Supplies Pty Ltd
1 — 1 15 Sep 8d 15 Sep Worst is Mule-V mast weldment, ready 17 Sep, 2 days late
waiting on ST-IB350-200UB
Shop floor
1 sub-assembly late
Kinghitter Series 4 mast weldment
BO-26-4136
Series 4 / RB800 / Rock Drill + Reversible SM Linkage · NC Equipment Ltd
1 — 1 15 Sep 9d 8 Sep Worst is Kinghitter Series 4 mast weldment, ready 16 Sep, 1 day late Shop floor
1 sub-assembly late
Mule mast weldment
BO-26-4140
Mule / UltraGlide · Te Kuiti Fencing Supplies Ltd
1 — 1 16 Sep 6d 15 Sep Worst is Mule mast weldment, ready 22 Sep, 4 days late
waiting on ST-IB350-200UB
Shop floor
1 sub-assembly late
Mule-V mast weldment
BO-26-4269
Mule-V / SM900 / Post Lifter · NC Equipment Ltd
1 — 1 18 Sep 8d 15 Sep Worst is Mule-V mast weldment, ready 24 Sep, 4 days late
waiting on ST-IB350-200UB
Shop floor
1 sub-assembly late
Kinghitter Series 2 mast weldment
BO-26-4152
Series 2 / RB800 · Gippsland Fencing Supplies Pty Ltd
1 — 1 18 Sep 6d 15 Sep Worst is Kinghitter Series 2 mast weldment, ready 22 Sep, 2 days late
waiting on ST-IB350-200UB
Shop floor
1 sub-assembly late
Kinghitter Series 2 mast weldment
BO-26-4154
Series 2 / SM600 / Rock Spike · Giltrap AgriZone Ltd
1 — 1 21 Sep 6d 15 Sep Worst is Kinghitter Series 2 mast weldment, ready 22 Sep, 1 day late
waiting on ST-IB350-200UB
Shop floor
1 sub-assembly late
Kinghitter Series 3 mast weldment
BO-26-4145
Series 3 / PB650 / Post Lifter · Southern Wide Machinery Ltd
1 — 1 22 Sep 7d 15 Sep Worst is Kinghitter Series 3 mast weldment, ready 23 Sep, 1 day late
waiting on ST-IB350-200UB
Shop floor
HY-MOT-DRILL-250
Rock drill motor 250cc
3 machines
3 0 3 25 Sep 42d 14 Aug
25 days late
PO-26-387 · 8 Oct
13 days late
1 sub-assembly late
Rock Drill
BO-26-4169
Mule-V / SM1000 / Rock Drill · Canterbury Fencing Supplies Ltd
1 — 1 29 Sep 3d 8 Oct Worst is Rock Drill, ready 12 Oct, 9 days late
waiting on HY-MOT-DRILL-250
Shop floor
HY-RAM-TELE-90
Telescopic lift ram 90 x 1500
4 machines
4 0 4 2 Oct 56d 7 Aug
32 days late
PO-26-388 · 20 Oct
18 days late
1 sub-assembly late
Ram set, telescopic mast
BO-26-4184
Ultra T2 Telescopic / SM900 · Kaikōura Rural Ltd
1 — 1 5 Oct 2d 20 Oct Worst is Ram set, telescopic mast, ready 21 Oct, 12 days late
waiting on HY-RAM-TELE-90
Shop floor
ST-IB350-310UB
Infrabuild 350 I-beam 310UB40, mill run
2 machines
14.8 0 14.8 6 Oct 77d 21 Jul
49 days late
PO-26-384 · 21 Nov
46 days late
2 sub-assemblies late
Ram set, telescopic mast, Rock Drill
BO-26-4180
Ultra T2 Telescopic / PB650 / Rock Drill · Webbline Agriculture Ltd
2 — 2 8 Oct 2d 20 Oct Worst is Ram set, telescopic mast, ready 21 Oct, 9 days late
waiting on HY-RAM-TELE-90
Shop floor
BR-SLEW-800
Slew ring 800mm, internal gear
2 machines
2 0 2 9 Oct 45d 25 Aug
14 days late
PO-26-392 · 13 Oct
4 days late
1 sub-assembly late
Ram set, telescopic mast
BO-26-4188
Ultra T2 Telescopic / UltraGlide · Pilbara Fencing Pty Ltd
1 — 1 14 Oct 2d 20 Oct Worst is Ram set, telescopic mast, ready 21 Oct, 5 days late
waiting on HY-RAM-TELE-90
Shop floor
HY-RAM-ROT-63
Rotate ram 63 x 500, twin
2 machines
2 0 2 16 Oct 42d 4 Sep
4 days late
PO-26-388 · 20 Oct
4 days late
1 sub-assembly late
RB800 base weldment
BO-26-4204
Series 4 / RB800 / HD Post Cap · Riverina Machinery Pty Ltd
1 — 1 16 Oct 6d 13 Oct Worst is RB800 base weldment, ready 20 Oct, 2 days late
waiting on BR-SLEW-800
Shop floor
HY-VB-WV-AB
Walvoil ActiveBlock proportional module
20 machines
20 0 20 19 Oct 98d 13 Jul
57 days late
PO-26-381 · 3 Nov
15 days late
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4265
Ultra G4 / SM900 / Rock Spike · Canterbury Fencing Supplies Ltd
1 — 1 19 Oct 1d 3 Nov Worst is Valve bank assembly, Walvoil ActiveBlock, ready 3 Nov, 11 days late
waiting on HY-VB-WV-AB
Shop floor
2 sub-assemblies late
Ultra T2 Telescopic mast weldment, Ram set, telescopic mast
BO-26-4198
Ultra T2 Telescopic / PB650 · Canterbury Fencing Supplies Ltd
2 — 2 20 Oct 11d 21 Nov Worst is Ultra T2 Telescopic mast weldment, ready 7 Dec, 34 days late
waiting on ST-IB350-310UB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4266
Ultra G4 / SM900 · Canterbury Fencing Supplies Ltd
1 — 1 20 Oct 1d 3 Nov Worst is Valve bank assembly, Walvoil ActiveBlock, ready 3 Nov, 10 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4202
Ultra G4 / MS350 · Canterbury Fencing Supplies Ltd
1 — 1 21 Oct 1d 3 Nov Worst is Valve bank assembly, Walvoil ActiveBlock, ready 3 Nov, 9 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4267
Ultra G4 / SM900 · Canterbury Fencing Supplies Ltd
1 — 1 21 Oct 1d 3 Nov Worst is Valve bank assembly, Walvoil ActiveBlock, ready 3 Nov, 9 days late
waiting on HY-VB-WV-AB
Shop floor
HY-JOY-PROP
Proportional joystick, ActiveBlock
11 machines
13 0 13 22 Oct 91d 23 Jul
47 days late
PO-26-381 · 3 Nov
12 days late
2 sub-assemblies late
Valve bank assembly, Walvoil ActiveBlock, PB650 base weldment
BO-26-4203
Mule-V / PB650 / Rock Spike · North Queensland Rural Pty Ltd
2 — 2 22 Oct 1d 3 Nov Worst is Valve bank assembly, Walvoil ActiveBlock, ready 3 Nov, 8 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
RB800 base weldment
BO-26-4212
Ultra G2S / RB800 · Central Otago Ag Ltd
1 — 1 26 Oct 6d 20 Oct Worst is RB800 base weldment, ready 27 Oct, 1 day late
waiting on HY-RAM-ROT-63
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4213
Contractor / SM600 / Auger · Waikato Fencing Systems Ltd
1 — 1 27 Oct 1d 3 Nov Worst is Valve bank assembly, Walvoil ActiveBlock, ready 3 Nov, 5 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4216
Contractor / SM600 · Northland Farm Machinery Ltd
1 — 1 30 Oct 1d 3 Nov Worst is Valve bank assembly, Walvoil ActiveBlock, ready 3 Nov, 2 days late
waiting on HY-VB-WV-AB
Shop floor
HY-VB-WV-SD11
Walvoil SD11 8-bank valve, hydraulic pilot
3 machines
3 0 3 3 Nov 105d 21 Jul
49 days late
PO-26-382 · 16 Dec
43 days late
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4220
Mule-V / SM900 · Waikato Fencing Systems Ltd
1 — 1 3 Nov 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 31 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4221
Ultra G4 / UltraGlide · Otago Farm Machinery Ltd
1 — 1 3 Nov 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 31 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil SD11 8-bank
BO-26-4224
Giant Disc 32 / 14-20t · Citycare Property Ltd
1 — 1 4 Nov 2d 16 Dec Worst is Valve bank assembly, Walvoil SD11 8-bank, ready 17 Dec, 31 days late
waiting on HY-VB-WV-SD11
Shop floor
AI-FAN-HYD
Hydraulic fan unit for air seeder
3 machines
3 0 3 5 Nov 42d 24 Sep Nothing on order
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4230
Mule-V / MS350 · Webbline Agriculture Ltd
1 — 1 6 Nov 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 28 days late
waiting on HY-VB-WV-AB
Shop floor
PL-SLIDE-UHMW-L
UHMW mast slide, large, adjustable
10 machines
40 2 38 9 Nov 11d 29 Oct Nothing on order
PL-INSERT-ADJ-32
Adjustable insert 32mm, threaded
9 machines
72 4 68 9 Nov 11d 29 Oct Nothing on order
HY-RAM-SIDE-75
Side shift ram 75 x 900
11 machines
11 0 11 11 Nov 42d 30 Sep Nothing on order
HY-HOSE-12-3600
Hose 2SN 12 dash, 3600mm, crimped both ends
14 machines
30 0 30 12 Nov 14d 29 Oct Nothing on order
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4229
Ultra G4 / SM1000 / HD Post Cap · Central Otago Ag Ltd
1 — 1 12 Nov 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 24 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4236
Ultra G4 / SM600 · QuikFence Australia Pty Ltd
1 — 1 16 Nov 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 22 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4237
Ultra G4 / UltraGlide · Marlborough Ag Ltd
1 — 1 17 Nov 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 21 days late
waiting on HY-VB-WV-AB
Shop floor
PT-2K-FPRED
Two pack enamel, FencePro red
8 machines
25.6 2.4 23.2 18 Nov 12d 6 Nov Nothing on order
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4233
Contractor / Digger / Auger · Timaru Tractor Services Ltd
1 — 1 19 Nov 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 19 days late
waiting on HY-VB-WV-AB
Shop floor
EL-LOOM-PROP
Wiring loom, proportional control
8 machines
9 0 9 23 Nov 28d 26 Oct Nothing on order
1 sub-assembly late
Ultra T2 Telescopic mast weldment
BO-26-4248
Ultra T2 Telescopic / SM900 · NC Equipment Ltd
1 — 1 23 Nov 11d 21 Nov Worst is Ultra T2 Telescopic mast weldment, ready 7 Dec, 10 days late
waiting on PL-SLIDE-UHMW-L
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil SD11 8-bank
BO-26-4241
Pile Driver 1200 / 14-20t · Downer New Zealand Ltd
1 — 1 24 Nov 2d 16 Dec Worst is Valve bank assembly, Walvoil SD11 8-bank, ready 17 Dec, 17 days late
waiting on HY-JOY-PROP
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4242
Contractor / PB650 · Waikato Fencing Systems Ltd
1 — 1 24 Nov 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 16 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4243
Contractor / SM600 / Chainsaw Holder · Murray Valley Ag Pty Ltd
1 — 1 25 Nov 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 15 days late
waiting on HY-VB-WV-AB
Shop floor
MX-ROLLER-REAR
Rear roller assembly
2 machines
2 0 2 27 Nov 18d 9 Nov Nothing on order
HY-VB-WV-SD5-4
Walvoil SD5 4-bank valve, cable control
5 machines
5 0 5 27 Nov 98d 21 Aug
18 days late
PO-26-382 · 16 Dec
19 days late
1 sub-assembly late
Valve bank assembly, Walvoil SD5 4-bank
BO-26-4250
Mule / Digger / Post Lifter · Whanganui Machinery Centre Ltd
1 — 1 27 Nov 1d 16 Dec Worst is Valve bank assembly, Walvoil SD5 4-bank, ready 16 Dec, 13 days late
waiting on HY-VB-WV-SD5-4
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4255
Contractor / PB650 · Murray Valley Ag Pty Ltd
1 — 1 2 Dec 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 10 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil SD5 4-bank
BO-26-4256
Mule / Digger · North Queensland Rural Pty Ltd
1 — 1 2 Dec 1d 16 Dec Worst is Valve bank assembly, Walvoil SD5 4-bank, ready 16 Dec, 10 days late
waiting on HY-VB-WV-SD5-4
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4249
Contractor / PB650 · Riverina Machinery Pty Ltd
1 — 1 3 Dec 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 9 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil SD5 4-bank
BO-26-4257
Mule / MS350 · NC Equipment Ltd
1 — 1 4 Dec 1d 16 Dec Worst is Valve bank assembly, Walvoil SD5 4-bank, ready 16 Dec, 8 days late
waiting on HY-VB-WV-SD5-4
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil SD11 8-bank
BO-26-4259
Rotary Mulcher 1800 / 14-20t · Fulton Hogan Ltd
1 — 1 7 Dec 2d 16 Dec Worst is Valve bank assembly, Walvoil SD11 8-bank, ready 17 Dec, 8 days late
waiting on HY-JOY-PROP
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4258
Ultra G4 / PB650 / RSE Turner · Pukekohe Ag Centre Ltd
1 — 1 7 Dec 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 7 days late
waiting on HY-VB-WV-AB
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil SD5 4-bank
BO-26-4262
Original / SM1000 / Leg Ram + RSE Turner · AGTEC Machinery Ltd
1 — 1 9 Dec 1d 16 Dec Worst is Valve bank assembly, Walvoil SD5 4-bank, ready 16 Dec, 5 days late
waiting on HY-VB-WV-SD5-4
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil SD5 4-bank
BO-26-4264
Series 3 / SM900 · Murray Valley Ag Pty Ltd
1 — 1 10 Dec 1d 16 Dec Worst is Valve bank assembly, Walvoil SD5 4-bank, ready 16 Dec, 4 days late
waiting on HY-VB-WV-SD5-4
Shop floor
1 sub-assembly late
Valve bank assembly, Walvoil ActiveBlock
BO-26-4268
Contractor / RB800 / Rock Drill · QuikFence Australia Pty Ltd
1 — 1 11 Dec 1d 16 Dec Worst is Valve bank assembly, Walvoil ActiveBlock, ready 16 Dec, 3 days late
waiting on HY-VB-WV-AB
Shop floor