PO-26-383

InfraBuild Steel · Australia · ETA 15 Sep 2026
GB Grant Sales Manager
InfraBuild Steel Sent Preferred
Raised7 Jul 2026
ETA15 Sep 2026
Raised byPriya Hemara
Supplier accountS-2002
TermsNET 30
ContactWayne Osborne · wayne.osborne@infrabuild.com

September mill run, grade 350 high tensile on the Kinghitter and FencePro section profile.

What this shipment decides
13

13 machines on the calendar are waiting on this order. 13 of them need their parts before it lands.

Order value A$91,680

Order lines

HARMONiQ
3 lines
ComponentOrderedReceivedOutstandingUnitValue
ST-IB350-200UB
Infrabuild 350 I-beam 200UB22, mill run
420 0 420 A$88 A$36,960
ST-IB350-250UB
Infrabuild 350 I-beam 250UB31, mill run
360 0 360 A$124 A$44,640
ST-IB350-150UB
Infrabuild 350 I-beam 150UB14, mill run
180 0 180 A$56 A$10,080

Machines waiting on this order

Platform
13
Build orderMachineWaiting onNeededLandsStatus
BO-26-4111 Mule / UltraGlide / Rock Spike ST-IB350-200UB 8 Sep 15 Sep +7d Late
BO-26-4130 Series 2 / Digger ST-IB350-200UB 8 Sep 15 Sep +7d Late
BO-26-4133 Mule / SM900 ST-IB350-200UB 8 Sep 15 Sep +7d At risk
BO-26-4134 Mule / SM1000 ST-IB350-200UB 8 Sep 15 Sep +7d At risk
BO-26-4135 Series 2 / PB650 ST-IB350-200UB 8 Sep 15 Sep +7d At risk
BO-26-4138 Mule-V / MS350 ST-IB350-200UB 8 Sep 15 Sep +7d At risk
BO-26-4139 Mule / PB650 / Reversible SM Linkage ST-IB350-200UB 8 Sep 15 Sep +7d At risk
BO-26-4140 Mule / UltraGlide ST-IB350-200UB 9 Sep 15 Sep +6d At risk
BO-26-4269 Mule-V / SM900 / Post Lifter ST-IB350-200UB 9 Sep 15 Sep +6d At risk
BO-26-4142 Mule / RB800 ST-IB350-200UB 10 Sep 15 Sep +5d On track
BO-26-4152 Series 2 / RB800 ST-IB350-200UB 11 Sep 15 Sep +4d At risk
BO-26-4145 Series 3 / PB650 / Post Lifter ST-IB350-200UB 14 Sep 15 Sep +1d On track
BO-26-4154 Series 2 / SM600 / Rock Spike ST-IB350-200UB 14 Sep 15 Sep +1d On track

Correspondence with this supplier

1 thread

September mill run — 200UB and 250UB confirmation

Wayne Osborne wayne.osborne@infrabuild.com Received
4 Sep 03:40
Hi Priya, The September run has come off the mill and is on the water. Napier discharge is two days before, and with the transfer to Palmerston North you should have it on 15 Sep 2026. Full quantities on the 200UB22 and the 250UB31, and the 150UB14 is on the same consignment. Mill certificates attached. Wayne
InfraBuild-mill-cert-350.pdf Packing-list-Sep.pdf