BO-26-4113

Maxam Multi-Cut 2100 Mounted for Whanganui Machinery Centre Ltd
NB Nathan General Manager
Maxam Multi-Cut 2100 / Mounted Late
Sales orderSO-26-1206 line 1
Serialassigned at QC sign-off
AttachmentsNone
Released11 Aug 2026
Final assembly31 Aug 2026
Promised to dealer7 Sep 2026

Rams arrived with the wrong pin centres and had to go back to Hydraflow.

Convergence date
8 Sep 2026

The last sub-assembly is not ready until 8 Sep 2026, which is 6 working days after final assembly is scheduled to start on 31 Aug 2026. This machine cannot be built on its date.

Critical path
Decal and document set, MX
On the bench, ready 8 Sep, needed 28 Aug
Onto the assembly bench 9 Sep 2026
Calculated completion 16 Sep 2026
Promised to dealer 7 Sep 2026

Production stages

Currently at stage 6 of 10 since 4 Sep 2026
  1. Released to production
    11 Aug
  2. Steel cut and prep
    12 Aug
  3. Fabrication and weld
    13 Aug
  4. Machining
    20 Aug
  5. Blast and paint
    24 Aug
  6. Hydraulic assembly
    26 Aug
  7. Final assembly
    31 Aug
  8. Test rig
    1 Sep
  9. QC sign-off
    3 Sep
  10. Ready for despatch
    4 Sep

Sub-assemblies

Platform
3 of 4 complete and in stores
Sub-assembly State Where Hours Required by Ready Verdict
Maxam 2100 deck weldment
Deck weldment · 4 day build · SA-DW-MX2100
In stores Stores 16.5 / 16.5 28 Aug 25 Aug Complete 25 Aug
Maxam 2100 drive pack
Drive pack · 2 day build · SA-DP-MX2100
In stores Stores 3 / 3 28 Aug 26 Aug Complete 26 Aug
Maxam 2100 rotor assembly
Rotor assembly · 2 day build · SA-RA-MX2100
In stores Stores 4.5 / 4.5 28 Aug 25 Aug Complete 25 Aug
Decal and document set, MX
Decal set · 1 day build · SA-DS-MX
On the bench ASSY · Grant Molloy 0.4 / 0.5 28 Aug 8 Sep 7 days late. Not enough days left to build it.

Value in this job

Standard cost
Material issued to date
$6,917
Labour booked to date
$1,260
Work in progress
$8,177
Material at standard, complete
$6,971
Labour at standard, complete
$1,817
Hours booked
27.4 / 39.5
Sold for
$14,288

HARMONiQ costing and stock valuation come from HARMONiQ.

Activity and correspondence

Component requirements

StockNetting
4 lines still to issue against this machine
Component For Required On hand Allocated ahead Available On order ETA Shortfall
DC-MANUAL-MX
Maxam operator manual and parts book
Decal and document set, MX 1 15 0 15 0 — —
DC-MX-TOPPER
Maxam Topper decal set
Decal and document set, MX 1 15 0 15 0 — —
DC-PLATE-SER
Serial and compliance plate, engraved
Decal and document set, MX 1 150 1 149 1 — —
DC-SAFETY-SET
Safety decal set, AS/NZS
Decal and document set, MX 1 150 1 149 1 — —