PO-26-381

Walvoil S.p.A. · Italy · ETA 3 Nov 2026
NB Nathan General Manager
Walvoil S.p.A. Sent Preferred
Raised4 Jul 2026
ETA3 Nov 2026
Raised byPriya Hemara
Supplier accountS-2001
TermsNET 45
ContactElena Baldi · e.baldi@walvoil.com

Revised by Walvoil on 18 August: the SD5 line was re-tooled and the sailing moved out by nineteen days.

What this shipment decides
7

7 machines on the calendar are waiting on this order. 7 of them need their parts before it lands.

Order value €32,900

Order lines

HARMONiQ
4 lines
ComponentOrderedReceivedOutstandingUnitValue
HY-VB-WV-AB
Walvoil ActiveBlock proportional module
5 0 5 €1,280 €6,400
HY-VB-WV-SD5-6
Walvoil SD5 6-bank valve, cable control
9 0 9 €1,460 €13,140
HY-JOY-PROP
Proportional joystick, ActiveBlock
12 0 12 €480 €5,760
HY-CTRL-CABLE-4
Cable control assembly, 4 lever
20 0 20 €380 €7,600

Machines waiting on this order

Platform
7
Build orderMachineWaiting onNeededLandsStatus
BO-26-4265 Ultra G4 / SM900 / Rock Spike HY-VB-WV-AB 19 Oct 3 Nov +15d At risk
BO-26-4266 Ultra G4 / SM900 HY-VB-WV-AB 20 Oct 3 Nov +14d At risk
BO-26-4202 Ultra G4 / MS350 HY-VB-WV-AB 21 Oct 3 Nov +13d At risk
BO-26-4267 Ultra G4 / SM900 HY-VB-WV-AB 21 Oct 3 Nov +13d At risk
BO-26-4203 Mule-V / PB650 / Rock Spike HY-JOY-PROP, HY-VB-WV-AB 22 Oct 3 Nov +12d At risk
BO-26-4213 Contractor / SM600 / Auger HY-JOY-PROP, HY-VB-WV-AB 27 Oct 3 Nov +7d At risk
BO-26-4216 Contractor / SM600 HY-JOY-PROP, HY-VB-WV-AB 30 Oct 3 Nov +4d At risk

Correspondence with this supplier

1 thread

Revised sailing — order PO-26-381, SD5 and ActiveBlock

Priya Hemara priya@farmgear.co.nz Sent
26 Aug 21:20
Ciao Elena, Checking in on PO-26-381. We have it landing with us on 15 Oct 2026 against your last confirmation. Can you confirm the vessel and the ETA into Napier? We have three Ultra G4 machines and a run of six banks committed against this shipment, so the date matters to us more than usual this time. Thanks, Priya
Elena Baldi e.baldi@walvoil.com Received
1 Sep 09:14
Dear Priya, I am sorry to write with this. The SD5 line here has been re-tooled for the new proportional spool and our production slot has moved. Your order PO-26-381 is now scheduled to ship on 26 Sep 2026 and the revised arrival into Napier is 3 Nov 2026. This is nineteen days later than we confirmed. The ActiveBlock modules are the affected line; the cable controls are unaffected and can travel with the same consignment. If you need a small quantity sooner we can look at air freight for up to four modules, but the cost is around €340 each. With apologies, Elena Baldi Walvoil S.p.A.
Walvoil-revised-schedule.pdf
Priya Hemara priya@farmgear.co.nz Sent
1 Sep 20:05
Archie, Grant — see below. The Walvoil ActiveBlock modules have moved to 3 Nov 2026. That is a fortnight after the Canterbury Fencing three Ultra G4 are scheduled onto the bench. I have flagged it against the build orders. Elena has offered air freight on up to four at about €340 each if we decide it is worth it. Priya