Revised sailing — order PO-26-381, SD5 and ActiveBlock
Priya Hemara priya@farmgear.co.nz Sent
26 Aug 21:20 Ciao Elena,
Checking in on PO-26-381. We have it landing with us on 15 Oct 2026 against your last confirmation. Can you confirm the vessel and the ETA into Napier?
We have three Ultra G4 machines and a run of six banks committed against this shipment, so the date matters to us more than usual this time.
Thanks,
Priya
Elena Baldi e.baldi@walvoil.com Received
1 Sep 09:14 Dear Priya,
I am sorry to write with this. The SD5 line here has been re-tooled for the new proportional spool and our production slot has moved. Your order PO-26-381 is now scheduled to ship on 26 Sep 2026 and the revised arrival into Napier is 3 Nov 2026.
This is nineteen days later than we confirmed. The ActiveBlock modules are the affected line; the cable controls are unaffected and can travel with the same consignment.
If you need a small quantity sooner we can look at air freight for up to four modules, but the cost is around €340 each.
With apologies,
Elena Baldi
Walvoil S.p.A.
Walvoil-revised-schedule.pdf
Priya Hemara priya@farmgear.co.nz Sent
1 Sep 20:05 Archie, Grant — see below. The Walvoil ActiveBlock modules have moved to 3 Nov 2026.
That is a fortnight after the Canterbury Fencing three Ultra G4 are scheduled onto the bench. I have flagged it against the build orders. Elena has offered air freight on up to four at about €340 each if we decide it is worth it.