Nathan Barnes, General Manager · Tue 8 Sep 2026
NB Nathan General Manager

Ninety day forward load

Machines scheduled per week against 14 a week of bench capacity. 1 week over.
Platform

The week of 28 Sep carries 18 machines against a standard mix capacity of 14. That is 29% over, and the capacity band on the production calendar shows which bench gives out first.

What is at risk

Platform
61 machines are not on their date

Long lead watchlist

StockCover
Cover against the forward order book
HY-VB-WV-AB 98 day lead · Walvoil S.p.A.
Walvoil ActiveBlock proportional module
On hand 15 Committed 35 On water 21 Next lands 3 Nov
Cover runs out 19 Oct on 20 machines. The next shipment lands 3 Nov, 15 days late.
HY-VB-WV-SD5-6 98 day lead · Walvoil S.p.A.
Walvoil SD5 6-bank valve, cable control
On hand 28 Committed 34 On water 9 Next lands 3 Nov
Covered for every build on the visible plan.
ST-IB350-250UB 70 day lead · InfraBuild Steel
Infrabuild 350 I-beam 250UB31, mill run
On hand 138.6 Committed 273.4 On water 840 Next lands 15 Sep
Covered for every build on the visible plan.
ST-IB350-200UB 70 day lead · InfraBuild Steel
Infrabuild 350 I-beam 200UB22, mill run
On hand 0 Committed 242.4 On water 720 Next lands 15 Sep
Cover runs out 8 Sep on 13 machines. The next shipment lands 15 Sep, 7 days late.
HY-RAM-SIDE-75 42 day lead · Hydraflow Industries Ltd
Side shift ram 75 x 900
On hand 25 Committed 56 On water 20 Next lands 3 Oct
Cover runs out 11 Nov on 11 machines, and there is nothing on order.
BR-SLEW-800 45 day lead · Saeco Bearings NZ Ltd
Slew ring 800mm, internal gear
On hand 5 Committed 14 On water 8 Next lands 13 Oct
Cover runs out 9 Oct on 2 machines. The next shipment lands 13 Oct, 4 days late.