Machines due in September
34
25 on track 5 at risk 4 late
Builds in progress
WIP value 65
$400k of work in progress
Component shortages blocking a build
18
10 passed the day the order had to be placed
Order book, next 90 days
HARMONiQ $4.44m
95 open orders · 14 quoted
Ninety day forward load
Machines scheduled per week against 14 a week of bench capacity. 1 week over.
Platform
The week of 28 Sep carries 18 machines against a standard mix capacity of 14. That is 29% over, and the capacity band on the production calendar shows which bench gives out first.
What is at risk
Platform
61 machines are not on their date
Series 3 / PB650 / Hinge Adapter + RSE Turner NC Equipment Ltd Late assembly 27 Aug Hydraulic pack, standard on the bench at HYD, ready 9 Sep against a required date of 26 Aug.
Multi-Cut 2100 / Mounted Whanganui Machinery Centre Ltd Late assembly 31 Aug Decal and document set, MX on the bench at ASSY, ready 8 Sep against a required date of 28 Aug.
Mule / SM900 Webbline Agriculture Ltd At risk assembly 15 Sep Mule mast weldment is waiting on ST-IB350-200UB, which lands 15 Sep — 7 days after it is needed.
Mule / SM1000 Waikato Fencing Systems Ltd At risk assembly 15 Sep Mule mast weldment is waiting on ST-IB350-200UB, which lands 15 Sep — 7 days after it is needed.
Series 2 / PB650 Giltrap AgriZone Ltd At risk assembly 15 Sep Kinghitter Series 2 mast weldment is waiting on ST-IB350-200UB, which lands 15 Sep — 7 days after it is needed.
Mule / PB650 / Reversible SM Linkage Otago Farm Machinery Ltd At risk assembly 16 Sep Mule mast weldment is waiting on ST-IB350-200UB, which lands 15 Sep — 7 days after it is needed.
Mule-V / MS350 Gippsland Fencing Supplies Pty Ltd At risk assembly 16 Sep Mule-V mast weldment is waiting on ST-IB350-200UB, which lands 15 Sep — 7 days after it is needed.
Mule-V / SM1000 / Rock Drill Canterbury Fencing Supplies Ltd At risk assembly 30 Sep Rock Drill is waiting on HY-MOT-DRILL-250, which lands 8 Oct — 13 days after it is needed.
Long lead watchlist
StockCover
Cover against the forward order book HY-VB-WV-AB 98 day lead · Walvoil S.p.A.
Walvoil ActiveBlock proportional module
Cover runs out 19 Oct on 20 machines. The next shipment lands 3 Nov, 15 days late.
HY-VB-WV-SD5-6 98 day lead · Walvoil S.p.A.
Walvoil SD5 6-bank valve, cable control
Covered for every build on the visible plan.
ST-IB350-250UB 70 day lead · InfraBuild Steel
Infrabuild 350 I-beam 250UB31, mill run
Covered for every build on the visible plan.
ST-IB350-200UB 70 day lead · InfraBuild Steel
Infrabuild 350 I-beam 200UB22, mill run
Cover runs out 8 Sep on 13 machines. The next shipment lands 15 Sep, 7 days late.
HY-RAM-SIDE-75 42 day lead · Hydraflow Industries Ltd
Side shift ram 75 x 900
Cover runs out 11 Nov on 11 machines, and there is nothing on order.
BR-SLEW-800 45 day lead · Saeco Bearings NZ Ltd
Slew ring 800mm, internal gear
Cover runs out 9 Oct on 2 machines. The next shipment lands 13 Oct, 4 days late.