PO-26-384

InfraBuild Steel · Australia · ETA 21 Nov 2026
NB Nathan General Manager
InfraBuild Steel Approved Preferred
Raised30 Aug 2026
ETA21 Nov 2026
Raised byPriya Hemara
Supplier accountS-2002
TermsNET 30
ContactWayne Osborne · wayne.osborne@infrabuild.com

November mill run. Ordered against the summer plan rather than a reorder point.

What this shipment decides
2

2 machines on the calendar are waiting on this order. 2 of them need their parts before it lands.

Order value A$111,840

Order lines

HARMONiQ
3 lines
ComponentOrderedReceivedOutstandingUnitValue
ST-IB350-250UB
Infrabuild 350 I-beam 250UB31, mill run
480 0 480 A$124 A$59,520
ST-IB350-310UB
Infrabuild 350 I-beam 310UB40, mill run
160 0 160 A$162 A$25,920
ST-IB350-200UB
Infrabuild 350 I-beam 200UB22, mill run
300 0 300 A$88 A$26,400

Machines waiting on this order

Platform
2
Build orderMachineWaiting onNeededLandsStatus
BO-26-4198 Ultra T2 Telescopic / PB650 ST-IB350-310UB 6 Oct 21 Nov +46d At risk
BO-26-4248 Ultra T2 Telescopic / SM900 ST-IB350-310UB 9 Nov 21 Nov +12d Blocked

Correspondence with this supplier

1 thread

September mill run — 200UB and 250UB confirmation

Wayne Osborne wayne.osborne@infrabuild.com Received
4 Sep 03:40
Hi Priya, The September run has come off the mill and is on the water. Napier discharge is two days before, and with the transfer to Palmerston North you should have it on 15 Sep 2026. Full quantities on the 200UB22 and the 250UB31, and the 150UB14 is on the same consignment. Mill certificates attached. Wayne
InfraBuild-mill-cert-350.pdf Packing-list-Sep.pdf