Production Calendar

Week of 19 Oct 2026 · 13 machines in view · capacity 14 a week
NB Nathan General Manager
← Today → Week of 19 Oct 2026
On track At risk Blocked or late Complete Platform

Capacity

Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward.
Station Available M 19 OctT 20 OctW 21 OctT 22 OctF 23 Oct
Cutting
2 on the tools · Rangi Whaanga
16 h 27% 84% 36% 24% 61%
Fabrication
8 on the tools · Dave Kemsley
64 h 82% 85% 98% 92% 67%
Machining
2 on the tools · Ivan Petrovic
16 h 52% 61% 38% 96% 104%
Paint
3 on the tools · Manu Tipene
24 h 64% 70% 89% 67% 56%
Hydraulics
4 on the tools · Shaun Corry
32 h 125% 79% 70% 53% 52%
Final Assembly
5 on the tools · Tui Fraser
40 h 26% 80% 130% 114% 60%
Test Rig
1 on the tools · Barry Mellsop
8 h 19% 25% 100% 113% 75%
QC
1 on the tools · Yvonne Tapsell
8 h 38% 13% 19% 75% 81%