NC Equipment Ltd Confirmed Dealer
Dealer referenceNCEQ-6614
Ordered1 Aug 2026
RepGB
SourceDealer order
HARMONiQ accountC-1024
HubSpot deal46050627
Promised three weeks before the machine can physically be finished. Nobody has told the dealer yet.
Delivery
- Promised to the dealer HARMONiQ
- 31 Aug 2026
- Calculated by the factory Platform
- 5 Oct 2026
These do not agree. The factory cannot finish this order until 5 Oct 2026, which is 25 working days after the date the dealer was given. That is a conversation to have now, not three weeks before delivery.
Order lines
1 configured machine
| Line | Configuration | Build order | Assembly | Completion | Status | Value | |
|---|---|---|---|---|---|---|---|
| 1 | | Mule-V / SM900 / Post Lifter Mule-V mast · Sidemount SM900 · Post Lifter Kit | BO-26-4269 | 21 Sep | 5 Oct | At risk | $23,287 |
| Order value, NZD, excluding GST | $23,287 | ||||||
| Dealer band 27% off a list price of | $31,900 | ||||||
Correspondence on this order
1 thread