Production Calendar

26 Oct 2026 · 2 machines in view · capacity 14 a week
NB Nathan General Manager
← Today → 26 Oct 2026
On track At risk Blocked or late Complete Platform

Mon 26 Oct 2026

2 machines onto the bench

Capacity

Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward.
Station Available M 26 Oct
Cutting
2 on the tools · Rangi Whaanga
16 h 26%
Fabrication
8 on the tools · Dave Kemsley
64 h 70%
Machining
2 on the tools · Ivan Petrovic
16 h 78%
Paint
3 on the tools · Manu Tipene
24 h 89%
Hydraulics
4 on the tools · Shaun Corry
32 h 52%
Final Assembly
5 on the tools · Tui Fraser
40 h 53%
Test Rig
1 on the tools · Barry Mellsop
8 h 25%
QC
1 on the tools · Yvonne Tapsell
8 h 56%