On track At risk Blocked or late Complete Platform
Wed 21 Oct 2026
4 machines onto the bench
BO-26-4198 Ultra T2 Telescopic / PB650 At risk
Canterbury Fencing Supplies Ltd · Released to production · convergence 7 Dec (33 days late)
77.8 h
0% ready
BO-26-4199 Giant Disc 24 / 14-20t On track
Downer New Zealand Ltd · Released to production · convergence 20 Oct
90.5 h
0% ready
BO-26-4200 Series 2 / RB800 On track
Canterbury Fencing Supplies Ltd · Released to production · convergence 20 Oct
66.1 h
0% ready
BO-26-4266 Ultra G4 / SM900 At risk
Canterbury Fencing Supplies Ltd · Released to production · convergence 3 Nov (9 days late)
65.5 h
0% ready
Capacity
Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward. | Station | Available | W 21 Oct |
|---|---|---|
| Cutting 2 on the tools · Rangi Whaanga | 16 h | 36% |
| Fabrication 8 on the tools · Dave Kemsley | 64 h | 98% |
| Machining 2 on the tools · Ivan Petrovic | 16 h | 38% |
| Paint 3 on the tools · Manu Tipene | 24 h | 89% |
| Hydraulics 4 on the tools · Shaun Corry | 32 h | 70% |
| Final Assembly 5 on the tools · Tui Fraser | 40 h | 130% |
| Test Rig 1 on the tools · Barry Mellsop | 8 h | 100% |
| QC 1 on the tools · Yvonne Tapsell | 8 h | 19% |