Series 3 / SM900 On track CustomerCochranes of Canterbury Ltd
Serialassigned at QC sign-off
MastKHS3
BaseSidemount SM900
AttachmentsNone
Released19 Aug 2026
Final assembly10 Sep 2026
Promised to dealer17 Sep 2026
Every sub-assembly complete and in stores. This is what it looks like when the plan works.
Convergence date
9 Sep 2026
Every sub-assembly is ready on or before 10 Sep 2026, the day final assembly is scheduled to start. This machine can be built on its date.
Critical path
Ram set, medium mast
Complete 9 Sep
Onto the assembly bench 11 Sep 2026
Calculated completion 22 Sep 2026
Promised to dealer 17 Sep 2026
Production stages
Currently at stage 6 of 10 since 7 Sep 2026
- Released to production19 Aug
- Steel cut and prep20 Aug
- Fabrication and weld21 Aug
- Machining31 Aug
- Blast and paint2 Sep
- Hydraulic assembly7 Sep
- Final assembly10 Sep
- Test rig14 Sep
- QC sign-off15 Sep
- Ready for despatch16 Sep
Sub-assemblies
Platform
7 of 7 complete and in stores | Sub-assembly | State | Where | Hours | Required by | Ready | Verdict |
|---|---|---|---|---|---|---|
| Kinghitter Series 3 mast weldment Mast weldment · 7 day build · SA-MW-KHS3 | In stores | Stores | 19.9 / 19.9 | 9 Sep | 7 Sep | Complete 7 Sep |
| Sidemount SM900 base weldment Base weldment · 4 day build · SA-BW-SM900 | In stores | Stores | 11.5 / 11.5 | 9 Sep | 7 Sep | Complete 7 Sep |
| Hydraulic pack, standard Hydraulic pack · 2 day build · SA-HP-STD | In stores | Stores | 2.5 / 2.5 | 9 Sep | 7 Sep | Complete 7 Sep |
| Valve bank assembly, Walvoil SD5 4-bank Valve bank · 1 day build · SA-VB-SD5-4 | In stores | Stores | 1.2 / 1.2 | 9 Sep | 4 Sep | Complete 4 Sep |
| Ram set, medium mast Ram set · 1 day build · SA-RS-M | In stores | Stores | 1.2 / 1.2 | 9 Sep | 9 Sep | Complete 9 Sep |
| Hose kit, medium mast Hose kit · 1 day build · SA-HK-M | In stores | Stores | 1.5 / 1.5 | 9 Sep | 7 Sep | Complete 7 Sep |
| Decal and document set, KH Decal set · 1 day build · SA-DS-KH | In stores | Stores | 0.5 / 0.5 | 9 Sep | 7 Sep | Complete 7 Sep |
Value in this job
Standard cost
- Material issued to date
- $10,410
- Labour booked to date
- $1,923
- Work in progress
- $12,333
- Material at standard, complete
- $10,410
- Labour at standard, complete
- $2,774
- Hours booked
- 41.8 / 60.3
- Sold for
- $21,600
HARMONiQ costing and stock valuation come from HARMONiQ.
Activity and correspondence
Released to production on 19 Aug 2026 against SO-26-1261. No correspondence is threaded to this machine.
Component requirements
StockNetting
0 lines still to issue against this machine | Component | For | Required | On hand | Allocated ahead | Available | On order | ETA | Shortfall |
|---|