BO-26-4270

Kinghitter Series 3 / Sidemount SM900 for Cochranes of Canterbury Ltd
NB Nathan General Manager
Kinghitter Series 3 / SM900 On track
Sales orderSO-26-1261 line 1
Serialassigned at QC sign-off
MastKHS3
BaseSidemount SM900
AttachmentsNone
Released19 Aug 2026
Final assembly10 Sep 2026
Promised to dealer17 Sep 2026

Every sub-assembly complete and in stores. This is what it looks like when the plan works.

Convergence date
9 Sep 2026

Every sub-assembly is ready on or before 10 Sep 2026, the day final assembly is scheduled to start. This machine can be built on its date.

Critical path
Ram set, medium mast
Complete 9 Sep
Onto the assembly bench 11 Sep 2026
Calculated completion 22 Sep 2026
Promised to dealer 17 Sep 2026

Production stages

Currently at stage 6 of 10 since 7 Sep 2026
  1. Released to production
    19 Aug
  2. Steel cut and prep
    20 Aug
  3. Fabrication and weld
    21 Aug
  4. Machining
    31 Aug
  5. Blast and paint
    2 Sep
  6. Hydraulic assembly
    7 Sep
  7. Final assembly
    10 Sep
  8. Test rig
    14 Sep
  9. QC sign-off
    15 Sep
  10. Ready for despatch
    16 Sep

Sub-assemblies

Platform
7 of 7 complete and in stores
Sub-assembly State Where Hours Required by Ready Verdict
Kinghitter Series 3 mast weldment
Mast weldment · 7 day build · SA-MW-KHS3
In stores Stores 19.9 / 19.9 9 Sep 7 Sep Complete 7 Sep
Sidemount SM900 base weldment
Base weldment · 4 day build · SA-BW-SM900
In stores Stores 11.5 / 11.5 9 Sep 7 Sep Complete 7 Sep
Hydraulic pack, standard
Hydraulic pack · 2 day build · SA-HP-STD
In stores Stores 2.5 / 2.5 9 Sep 7 Sep Complete 7 Sep
Valve bank assembly, Walvoil SD5 4-bank
Valve bank · 1 day build · SA-VB-SD5-4
In stores Stores 1.2 / 1.2 9 Sep 4 Sep Complete 4 Sep
Ram set, medium mast
Ram set · 1 day build · SA-RS-M
In stores Stores 1.2 / 1.2 9 Sep 9 Sep Complete 9 Sep
Hose kit, medium mast
Hose kit · 1 day build · SA-HK-M
In stores Stores 1.5 / 1.5 9 Sep 7 Sep Complete 7 Sep
Decal and document set, KH
Decal set · 1 day build · SA-DS-KH
In stores Stores 0.5 / 0.5 9 Sep 7 Sep Complete 7 Sep

Value in this job

Standard cost
Material issued to date
$10,410
Labour booked to date
$1,923
Work in progress
$12,333
Material at standard, complete
$10,410
Labour at standard, complete
$2,774
Hours booked
41.8 / 60.3
Sold for
$21,600

HARMONiQ costing and stock valuation come from HARMONiQ.

Activity and correspondence

Released to production on 19 Aug 2026 against SO-26-1261. No correspondence is threaded to this machine.

Component requirements

StockNetting
0 lines still to issue against this machine
Component For Required On hand Allocated ahead Available On order ETA Shortfall