Contractor / PB650 Complete CustomerDelmade Pty Ltd
SerialKH26-4834
MastKHCONTR
BasePB650
AttachmentsNone
Released7 Aug 2026
Final assembly1 Sep 2026
Promised to dealer1 Sep 2026
Convergence date
31 Aug 2026
Every sub-assembly is ready on or before 1 Sep 2026, the day final assembly is scheduled to start. This machine can be built on its date.
Critical path
Kinghitter Contractor mast weldment
Complete 31 Aug
Onto the assembly bench 1 Sep 2026
Calculated completion 9 Sep 2026
Promised to dealer 1 Sep 2026
Production stages
Currently at stage 10 of 10 since 7 Sep 2026
- Released to production7 Aug
- Steel cut and prep10 Aug
- Fabrication and weld11 Aug
- Machining21 Aug
- Blast and paint25 Aug
- Hydraulic assembly28 Aug
- Final assembly1 Sep
- Test rig3 Sep
- QC sign-off4 Sep
- Ready for despatch7 Sep
Sub-assemblies
Platform
7 of 7 complete and in stores | Sub-assembly | State | Where | Hours | Required by | Ready | Verdict |
|---|---|---|---|---|---|---|
| Kinghitter Contractor mast weldment Mast weldment · 10 day build · SA-MW-KHCONTR | In stores | Stores | 26 / 26 | 31 Aug | 31 Aug | Complete 31 Aug |
| PB650 base weldment Base weldment · 5 day build · SA-BW-PB650 | In stores | Stores | 16.1 / 16.1 | 31 Aug | 26 Aug | Complete 26 Aug |
| Hydraulic pack, ActiveBlock Hydraulic pack · 2 day build · SA-HP-AB | In stores | Stores | 3 / 3 | 31 Aug | 27 Aug | Complete 27 Aug |
| Valve bank assembly, Walvoil ActiveBlock Valve bank · 1 day build · SA-VB-AB | In stores | Stores | 2 / 2 | 31 Aug | 26 Aug | Complete 26 Aug |
| Ram set, large mast Ram set · 1 day build · SA-RS-L | In stores | Stores | 1.5 / 1.5 | 31 Aug | 27 Aug | Complete 27 Aug |
| Hose kit, large mast Hose kit · 1 day build · SA-HK-L | In stores | Stores | 2 / 2 | 31 Aug | 31 Aug | Complete 31 Aug |
| Decal and document set, KH Decal set · 1 day build · SA-DS-KH | In stores | Stores | 0.5 / 0.5 | 31 Aug | 28 Aug | Complete 28 Aug |
Value in this job
Standard cost
- Material issued to date
- $14,852
- Labour booked to date
- $3,363
- Work in progress
- $18,214
- Material at standard, complete
- $14,852
- Labour at standard, complete
- $3,363
- Hours booked
- 73.1 / 73.1
- Sold for
- A$31,710
HARMONiQ costing and stock valuation come from HARMONiQ.
Activity and correspondence
Component requirements
StockNetting
0 lines still to issue against this machine | Component | For | Required | On hand | Allocated ahead | Available | On order | ETA | Shortfall |
|---|