BO-26-4114

FencePro Mule-V / MS350 Mastshift for Hawke's Bay Tractors Ltd
NB Nathan General Manager
FencePro Mule-V / MS350 Complete
Sales orderSO-26-1207 line 1
SerialFP26-4832
MastMule-V
BaseMS350 Mastshift
AttachmentsNone
Released7 Aug 2026
Final assembly31 Aug 2026
Promised to dealer7 Sep 2026
Convergence date
28 Aug 2026

Every sub-assembly is ready on or before 31 Aug 2026, the day final assembly is scheduled to start. This machine can be built on its date.

Critical path
Ram set, medium mast
Complete 28 Aug
Onto the assembly bench 31 Aug 2026
Calculated completion 9 Sep 2026
Promised to dealer 7 Sep 2026

Production stages

Currently at stage 10 of 10 since 4 Sep 2026
  1. Released to production
    7 Aug
  2. Steel cut and prep
    10 Aug
  3. Fabrication and weld
    11 Aug
  4. Machining
    20 Aug
  5. Blast and paint
    21 Aug
  6. Hydraulic assembly
    25 Aug
  7. Final assembly
    31 Aug
  8. Test rig
    2 Sep
  9. QC sign-off
    3 Sep
  10. Ready for despatch
    4 Sep

Sub-assemblies

Platform
7 of 7 complete and in stores
Sub-assembly State Where Hours Required by Ready Verdict
Mule-V mast weldment
Mast weldment · 8 day build · SA-MW-MULEV
In stores Stores 21.2 / 21.2 28 Aug 26 Aug Complete 26 Aug
MS350 Mastshift base weldment
Base weldment · 4 day build · SA-BW-MS350
In stores Stores 12.3 / 12.3 28 Aug 27 Aug Complete 27 Aug
Hydraulic pack, ActiveBlock
Hydraulic pack · 2 day build · SA-HP-AB
In stores Stores 3 / 3 28 Aug 27 Aug Complete 27 Aug
Valve bank assembly, Walvoil ActiveBlock
Valve bank · 1 day build · SA-VB-AB
In stores Stores 2 / 2 28 Aug 25 Aug Complete 25 Aug
Ram set, medium mast
Ram set · 1 day build · SA-RS-M
In stores Stores 1.2 / 1.2 28 Aug 28 Aug Complete 28 Aug
Hose kit, medium mast
Hose kit · 1 day build · SA-HK-M
In stores Stores 1.5 / 1.5 28 Aug 26 Aug Complete 26 Aug
Decal and document set, FP
Decal set · 1 day build · SA-DS-FP
In stores Stores 0.5 / 0.5 28 Aug 27 Aug Complete 27 Aug

Value in this job

Standard cost
Material issued to date
$11,766
Labour booked to date
$2,930
Work in progress
$14,696
Material at standard, complete
$11,766
Labour at standard, complete
$2,930
Hours booked
63.7 / 63.7
Sold for
$22,725

HARMONiQ costing and stock valuation come from HARMONiQ.

Activity and correspondence

Component requirements

StockNetting
0 lines still to issue against this machine
Component For Required On hand Allocated ahead Available On order ETA Shortfall