Mule-V / MS350 Complete CustomerHawke's Bay Tractors Ltd
SerialFP26-4832
MastMule-V
BaseMS350 Mastshift
AttachmentsNone
Released7 Aug 2026
Final assembly31 Aug 2026
Promised to dealer7 Sep 2026
Convergence date
28 Aug 2026
Every sub-assembly is ready on or before 31 Aug 2026, the day final assembly is scheduled to start. This machine can be built on its date.
Critical path
Ram set, medium mast
Complete 28 Aug
Onto the assembly bench 31 Aug 2026
Calculated completion 9 Sep 2026
Promised to dealer 7 Sep 2026
Production stages
Currently at stage 10 of 10 since 4 Sep 2026
- Released to production7 Aug
- Steel cut and prep10 Aug
- Fabrication and weld11 Aug
- Machining20 Aug
- Blast and paint21 Aug
- Hydraulic assembly25 Aug
- Final assembly31 Aug
- Test rig2 Sep
- QC sign-off3 Sep
- Ready for despatch4 Sep
Sub-assemblies
Platform
7 of 7 complete and in stores | Sub-assembly | State | Where | Hours | Required by | Ready | Verdict |
|---|---|---|---|---|---|---|
| Mule-V mast weldment Mast weldment · 8 day build · SA-MW-MULEV | In stores | Stores | 21.2 / 21.2 | 28 Aug | 26 Aug | Complete 26 Aug |
| MS350 Mastshift base weldment Base weldment · 4 day build · SA-BW-MS350 | In stores | Stores | 12.3 / 12.3 | 28 Aug | 27 Aug | Complete 27 Aug |
| Hydraulic pack, ActiveBlock Hydraulic pack · 2 day build · SA-HP-AB | In stores | Stores | 3 / 3 | 28 Aug | 27 Aug | Complete 27 Aug |
| Valve bank assembly, Walvoil ActiveBlock Valve bank · 1 day build · SA-VB-AB | In stores | Stores | 2 / 2 | 28 Aug | 25 Aug | Complete 25 Aug |
| Ram set, medium mast Ram set · 1 day build · SA-RS-M | In stores | Stores | 1.2 / 1.2 | 28 Aug | 28 Aug | Complete 28 Aug |
| Hose kit, medium mast Hose kit · 1 day build · SA-HK-M | In stores | Stores | 1.5 / 1.5 | 28 Aug | 26 Aug | Complete 26 Aug |
| Decal and document set, FP Decal set · 1 day build · SA-DS-FP | In stores | Stores | 0.5 / 0.5 | 28 Aug | 27 Aug | Complete 27 Aug |
Value in this job
Standard cost
- Material issued to date
- $11,766
- Labour booked to date
- $2,930
- Work in progress
- $14,696
- Material at standard, complete
- $11,766
- Labour at standard, complete
- $2,930
- Hours booked
- 63.7 / 63.7
- Sold for
- $22,725
HARMONiQ costing and stock valuation come from HARMONiQ.
Activity and correspondence
Component requirements
StockNetting
0 lines still to issue against this machine | Component | For | Required | On hand | Allocated ahead | Available | On order | ETA | Shortfall |
|---|