Mule / MS350 / Auger Complete CustomerKaikōura Rural Ltd
SerialFP26-4828
MastMule
BaseMS350 Mastshift
AttachmentsHydraulic Auger
Released3 Aug 2026
Final assembly28 Aug 2026
Promised to dealer4 Sep 2026
Convergence date
27 Aug 2026
Every sub-assembly is ready on or before 28 Aug 2026, the day final assembly is scheduled to start. This machine can be built on its date.
Critical path
MS350 Mastshift base weldment
Complete 27 Aug
Onto the assembly bench 28 Aug 2026
Calculated completion 8 Sep 2026
Promised to dealer 4 Sep 2026
Production stages
Currently at stage 10 of 10 since 4 Sep 2026
- Released to production3 Aug
- Steel cut and prep4 Aug
- Fabrication and weld5 Aug
- Machining13 Aug
- Blast and paint17 Aug
- Hydraulic assembly21 Aug
- Final assembly28 Aug
- Test rig2 Sep
- QC sign-off3 Sep
- Ready for despatch4 Sep
Sub-assemblies
Platform
8 of 8 complete and in stores | Sub-assembly | State | Where | Hours | Required by | Ready | Verdict |
|---|---|---|---|---|---|---|
| Mule mast weldment Mast weldment · 6 day build · SA-MW-MULE | In stores | Stores | 17.7 / 17.7 | 27 Aug | 25 Aug | Complete 25 Aug |
| MS350 Mastshift base weldment Base weldment · 4 day build · SA-BW-MS350 | In stores | Stores | 12.3 / 12.3 | 27 Aug | 27 Aug | Complete 27 Aug |
| Hydraulic pack, standard Hydraulic pack · 2 day build · SA-HP-STD | In stores | Stores | 2.5 / 2.5 | 27 Aug | 24 Aug | Complete 24 Aug |
| Valve bank assembly, Walvoil SD5 4-bank Valve bank · 1 day build · SA-VB-SD5-4 | In stores | Stores | 1.2 / 1.2 | 27 Aug | 24 Aug | Complete 24 Aug |
| Ram set, medium mast Ram set · 1 day build · SA-RS-M | In stores | Stores | 1.2 / 1.2 | 27 Aug | 27 Aug | Complete 27 Aug |
| Hose kit, medium mast Hose kit · 1 day build · SA-HK-M | In stores | Stores | 1.5 / 1.5 | 27 Aug | 25 Aug | Complete 25 Aug |
| Decal and document set, FP Decal set · 1 day build · SA-DS-FP | In stores | Stores | 0.5 / 0.5 | 27 Aug | 26 Aug | Complete 26 Aug |
| Hydraulic Auger Attachment kit · 3 day build · SA-AK-AUGER | In stores | Stores | 5.1 / 5.1 | 27 Aug | 26 Aug | Complete 26 Aug |
Value in this job
Standard cost
- Material issued to date
- $12,137
- Labour booked to date
- $2,944
- Work in progress
- $15,081
- Material at standard, complete
- $12,137
- Labour at standard, complete
- $2,944
- Hours booked
- 64 / 64
- Sold for
- $27,370
HARMONiQ costing and stock valuation come from HARMONiQ.
Activity and correspondence
Component requirements
StockNetting
0 lines still to issue against this machine | Component | For | Required | On hand | Allocated ahead | Available | On order | ETA | Shortfall |
|---|