BO-26-4103

FencePro Ultra G4 / RB800 for Otago Farm Machinery Ltd
NB Nathan General Manager
FencePro Ultra G4 / RB800 On track
Sales orderSO-26-1185 line 1
Serialassigned at QC sign-off
MastUltra G4
BaseRB800
AttachmentsNone
Released3 Aug 2026
Final assembly26 Aug 2026
Promised to dealer2 Sep 2026

Weldment came back off the blast bay with a weld that needed re-running.

Convergence date
25 Aug 2026

Every sub-assembly is ready on or before 26 Aug 2026, the day final assembly is scheduled to start. This machine can be built on its date.

Critical path
Hose kit, large mast
Complete 25 Aug
Onto the assembly bench 8 Sep 2026
Calculated completion 14 Sep 2026
Promised to dealer 2 Sep 2026

Production stages

Currently at stage 7 of 10 since 1 Sep 2026
  1. Released to production
    3 Aug
  2. Steel cut and prep
    4 Aug
  3. Fabrication and weld
    5 Aug
  4. Machining
    14 Aug
  5. Blast and paint
    19 Aug
  6. Hydraulic assembly
    24 Aug
  7. Final assembly
    26 Aug
  8. Test rig
    28 Aug
  9. QC sign-off
    31 Aug
  10. Ready for despatch
    1 Sep

Sub-assemblies

Platform
7 of 7 complete and in stores
Sub-assembly State Where Hours Required by Ready Verdict
Ultra G4 mast weldment
Mast weldment · 9 day build · SA-MW-ULTRAG4
In stores Stores 23 / 23 25 Aug 24 Aug Complete 24 Aug
RB800 base weldment
Base weldment · 6 day build · SA-BW-RB800
In stores Stores 19.2 / 19.2 25 Aug 24 Aug Complete 24 Aug
Hydraulic pack, ActiveBlock
Hydraulic pack · 2 day build · SA-HP-AB
In stores Stores 3 / 3 25 Aug 21 Aug Complete 21 Aug
Valve bank assembly, Walvoil ActiveBlock
Valve bank · 1 day build · SA-VB-AB
In stores Stores 2 / 2 25 Aug 24 Aug Complete 24 Aug
Ram set, large mast
Ram set · 1 day build · SA-RS-L
In stores Stores 1.5 / 1.5 25 Aug 20 Aug Complete 20 Aug
Hose kit, large mast
Hose kit · 1 day build · SA-HK-L
In stores Stores 2 / 2 25 Aug 25 Aug Complete 25 Aug
Decal and document set, FP
Decal set · 1 day build · SA-DS-FP
In stores Stores 0.5 / 0.5 25 Aug 21 Aug Complete 21 Aug

Value in this job

Standard cost
Material issued to date
$15,253
Labour booked to date
$2,654
Work in progress
$17,907
Material at standard, complete
$15,253
Labour at standard, complete
$3,367
Hours booked
57.7 / 73.2
Sold for
$33,744

HARMONiQ costing and stock valuation come from HARMONiQ.

Activity and correspondence

Component requirements

StockNetting
0 lines still to issue against this machine
Component For Required On hand Allocated ahead Available On order ETA Shortfall