Weeks shown
13
Weeks with a bench over capacity
2
Bench hours a week
1,040
Bench load
Platform
13 rows · run 7 Sep 19:40 | Week beginning | Cutting | Fabrication | Machining | Paint | Hydraulics | Final Assembly | Test Rig | QC | Machines |
|---|---|---|---|---|---|---|---|---|---|
| 7 Sep 2026 | 27% | 36% | 51% | 55% | 75% | 66% | 55% | 34% | 11 |
| 14 Sep 2026 | 94% | 91% | 38% | 60% | 60% | 73% | 59% | 48% | 12 |
| 21 Sep 2026 | 55% | 129% | 114% | 103% | 94% | 77% | 63% | 48% | 13 |
| 28 Sep 2026 | 60% | 78% | 99% | 113% | 91% | 116% | 89% | 60% | 18 |
| 5 Oct 2026 | 51% | 82% | 84% | 67% | 65% | 79% | 68% | 55% | 12 |
| 12 Oct 2026 | 50% | 77% | 76% | 94% | 61% | 65% | 51% | 39% | 10 |
| 19 Oct 2026 | 46% | 85% | 70% | 69% | 76% | 82% | 66% | 45% | 13 |
| 26 Oct 2026 | 30% | 66% | 69% | 85% | 59% | 67% | 53% | 44% | 10 |
| 2 Nov 2026 | 28% | 45% | 43% | 49% | 53% | 66% | 56% | 40% | 10 |
| 9 Nov 2026 | 42% | 58% | 47% | 48% | 41% | 48% | 36% | 30% | 8 |
| 16 Nov 2026 | 44% | 60% | 54% | 57% | 43% | 46% | 38% | 26% | 8 |
| 23 Nov 2026 | 39% | 69% | 47% | 59% | 40% | 52% | 41% | 31% | 8 |
| 30 Nov 2026 | 11% | 43% | 81% | 60% | 44% | 51% | 41% | 30% | 8 |
Hours loaded against hours available at every station, week by week, from the sub-assembly routes and the machine stages. Built by the Farmgear Operations Platform from live data on 8 Sep 2026. Stock, orders and costing are read from HARMONiQ; deals and campaigns from HubSpot; dates and readiness are calculated by the Platform.