Shortage and action list

What has to be ordered or made right now so that nothing stops?
NB Nathan General Manager
CSV All reports
Items short
10
Decisions already late
10
Nothing on order
0
Machines affected
49
Value to order
$67k

Shortage and action list

Platform
10 rows · run 7 Sep 19:40
ItemDescriptionSupplierMachinesRequiredAvailableShortNeededLeadOrder byCoverAction
ST-IB350-200UB Infrabuild 350 I-beam 200UB22, mill run InfraBuild Steel 13 65.4 0 65.4 8 Sep 70d 30 Jun (70d late) PO-26-383 · 15 Sep Order
HY-MOT-DRILL-250 Rock drill motor 250cc Hydraflow Industries Ltd 3 3 0 3 25 Sep 42d 14 Aug (25d late) PO-26-387 · 8 Oct Order
HY-RAM-TELE-90 Telescopic lift ram 90 x 1500 Hydraflow Industries Ltd 4 4 0 4 2 Oct 56d 7 Aug (32d late) PO-26-388 · 20 Oct Order
ST-IB350-310UB Infrabuild 350 I-beam 310UB40, mill run InfraBuild Steel 2 14.8 0 14.8 6 Oct 77d 21 Jul (49d late) PO-26-384 · 21 Nov Order
BR-SLEW-800 Slew ring 800mm, internal gear Saeco Bearings NZ Ltd 2 2 0 2 9 Oct 45d 25 Aug (14d late) PO-26-392 · 13 Oct Order
HY-RAM-ROT-63 Rotate ram 63 x 500, twin Hydraflow Industries Ltd 2 2 0 2 16 Oct 42d 4 Sep (4d late) PO-26-388 · 20 Oct Order
HY-VB-WV-AB Walvoil ActiveBlock proportional module Walvoil S.p.A. 20 20 0 20 19 Oct 98d 13 Jul (57d late) PO-26-381 · 3 Nov Order
HY-JOY-PROP Proportional joystick, ActiveBlock Walvoil S.p.A. 11 13 0 13 22 Oct 91d 23 Jul (47d late) PO-26-381 · 3 Nov Order
HY-VB-WV-SD11 Walvoil SD11 8-bank valve, hydraulic pilot Walvoil S.p.A. 3 3 0 3 3 Nov 105d 21 Jul (49d late) PO-26-382 · 16 Dec Order
HY-VB-WV-SD5-4 Walvoil SD5 4-bank valve, cable control Walvoil S.p.A. 5 5 0 5 27 Nov 98d 21 Aug (18d late) PO-26-382 · 16 Dec Order

Every component that will not be on the rack in time, sorted by the day the shortage bites, with the day the decision was due. Built by the Farmgear Operations Platform from live data on 8 Sep 2026. Stock, orders and costing are read from HARMONiQ; deals and campaigns from HubSpot; dates and readiness are calculated by the Platform.