Production Calendar

5 Nov 2103 to 14 Dec 2103 · 0 machines in view · capacity 14 a week
NB Nathan General Manager
← Today → 5 Nov 2103 to 14 Dec 2103
Clear
Stages Released to production Cutting Fabrication Machining Paint Hydraulics Final Assembly Test Rig QC Ready for despatch where it is now slip past the booked date Platform
Machine
w/c 5 Nov
w/c 12 Nov
w/c 19 Nov
w/c 26 Nov
w/c 3 Dec
w/c 10 Dec
M
5
T
6
W
7
T
8
F
9
M
12
T
13
W
14
T
15
F
16
M
19
T
20
W
21
T
22
F
23
M
26
T
27
W
28
T
29
F
30
M
3
T
4
W
5
T
6
F
7
M
10
T
11
W
12
T
13
F
14
Nothing matches.
Clear the filters to see the whole plan.

Capacity

Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward.