Production Calendar

22 Jan 2029 to 4 May 2029 · 0 machines in view · capacity 14 a week
NB Nathan General Manager
← Today → 22 Jan 2029 to 4 May 2029
Stages Released to production Cutting Fabrication Machining Paint Hydraulics Final Assembly Test Rig QC Ready for despatch where it is now slip past the booked date Platform
Machine
w/c 22 Jan
w/c 29 Jan
w/c 5 Feb
w/c 12 Feb
w/c 19 Feb
w/c 26 Feb
w/c 5 Mar
w/c 12 Mar
w/c 19 Mar
w/c 26 Mar
w/c 2 Apr
w/c 9 Apr
w/c 16 Apr
w/c 23 Apr
w/c 30 Apr
M
22
T
23
W
24
T
25
F
26
M
29
T
30
W
31
T
1
F
2
M
5
T
6
W
7
T
8
F
9
M
12
T
13
W
14
T
15
F
16
M
19
T
20
W
21
T
22
F
23
M
26
T
27
W
28
T
1
F
2
M
5
T
6
W
7
T
8
F
9
M
12
T
13
W
14
T
15
F
16
M
19
T
20
W
21
T
22
F
23
M
26
T
27
W
28
T
29
F
30
M
2
T
3
W
4
T
5
F
6
M
9
T
10
W
11
T
12
F
13
M
16
T
17
W
18
T
19
F
20
M
23
T
24
W
25
T
26
F
27
M
30
T
1
W
2
T
3
F
4
Nothing matches.
Clear the filters to see the whole plan.

Capacity

Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward.