Production Calendar

Week of 24 May 2027 · 0 machines in view · capacity 14 a week
NB Nathan General Manager
← Today → Week of 24 May 2027
Clear
On track At risk Blocked or late Complete Platform
Mon 24 May CUT 0%
—
Tue 25 May CUT 0%
—
Wed 26 May CUT 0%
—
Thu 27 May CUT 0%
—
Fri 28 May CUT 0%
—

Capacity

Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward.
Station Available M 24 MayT 25 MayW 26 MayT 27 MayF 28 May
Cutting
2 on the tools · Rangi Whaanga
16 h 0% 0% 0% 0% 0%
Fabrication
8 on the tools · Dave Kemsley
64 h 0% 0% 0% 0% 0%
Machining
2 on the tools · Ivan Petrovic
16 h 0% 0% 0% 0% 0%
Paint
3 on the tools · Manu Tipene
24 h 0% 0% 0% 0% 0%
Hydraulics
4 on the tools · Shaun Corry
32 h 0% 0% 0% 0% 0%
Final Assembly
5 on the tools · Tui Fraser
40 h 0% 0% 0% 0% 0%
Test Rig
1 on the tools · Barry Mellsop
8 h 0% 0% 0% 0% 0%
QC
1 on the tools · Yvonne Tapsell
8 h 0% 0% 0% 0% 0%