Production Calendar

Week of 7 Dec 2026 · 8 machines in view · capacity 14 a week
NB Nathan General Manager
← Today → Week of 7 Dec 2026
On track At risk Blocked or late Complete Platform

Capacity

Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward.
Station Available M 7 DecT 8 DecW 9 DecT 10 DecF 11 Dec
Cutting
2 on the tools · Rangi Whaanga
16 h 9% 0% 0% 0% 0%
Fabrication
8 on the tools · Dave Kemsley
64 h 18% 18% 17% 8% 0%
Machining
2 on the tools · Ivan Petrovic
16 h 55% 22% 13% 9% 28%
Paint
3 on the tools · Manu Tipene
24 h 66% 51% 15% 11% 13%
Hydraulics
4 on the tools · Shaun Corry
32 h 41% 45% 27% 14% 19%
Final Assembly
5 on the tools · Tui Fraser
40 h 35% 53% 65% 56% 45%
Test Rig
1 on the tools · Barry Mellsop
8 h 25% 25% 63% 44% 50%
QC
1 on the tools · Yvonne Tapsell
8 h 38% 19% 19% 44% 31%