Production Calendar

20 Oct 2026 · 0 machines in view · capacity 14 a week
NB Nathan General Manager
← Today → 20 Oct 2026
Clear
On track At risk Blocked or late Complete Platform

Tue 20 Oct 2026

0 machines onto the bench
Nothing is booked onto the assembly bench on 20 Oct 2026. The benches are still loaded — the capacity band below shows the sub-assembly work running that day.

Capacity

Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward.
Station Available T 20 Oct
Cutting
2 on the tools · Rangi Whaanga
16 h 84%
Fabrication
8 on the tools · Dave Kemsley
64 h 85%
Machining
2 on the tools · Ivan Petrovic
16 h 61%
Paint
3 on the tools · Manu Tipene
24 h 70%
Hydraulics
4 on the tools · Shaun Corry
32 h 79%
Final Assembly
5 on the tools · Tui Fraser
40 h 80%
Test Rig
1 on the tools · Barry Mellsop
8 h 25%
QC
1 on the tools · Yvonne Tapsell
8 h 13%