On track At risk Blocked or late Complete Platform
Mon 31 Aug QC 19%
—
Tue 1 Sep ASSY 40%
—
Wed 2 Sep TEST 50%
Thu 3 Sep TEST 75%
—
Mon 7 Sep HYD 26%
—
Tue 8 Sep HYD 195%
—
Wed 9 Sep MACH 171%
—
Thu 10 Sep PAINT 138%
—
Fri 11 Sep TEST 75%
—
Mon 14 Sep CUT 57%
—
Tue 15 Sep CUT 149%
—
Wed 16 Sep CUT 119%
—
Thu 17 Sep FAB 122%
—
Fri 18 Sep FAB 162%
—
Mon 21 Sep FAB 136%
—
Tue 22 Sep FAB 137%
—
Wed 23 Sep PAINT 171%
—
Thu 24 Sep FAB 135%
—
Fri 25 Sep MACH 180%
—
Mon 28 Sep MACH 194%
—
Tue 29 Sep PAINT 160%
—
Wed 30 Sep ASSY 158%
—
Thu 1 Oct ASSY 139%
—
Fri 2 Oct QC 100%
—
Capacity
Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward. | Station | Available | M 31 Aug | T 1 Sep | W 2 Sep | T 3 Sep | F 4 Sep | M 7 Sep | T 8 Sep | W 9 Sep | T 10 Sep | F 11 Sep | M 14 Sep | T 15 Sep | W 16 Sep | T 17 Sep | F 18 Sep | M 21 Sep | T 22 Sep | W 23 Sep | T 24 Sep | F 25 Sep |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Cutting 2 on the tools · Rangi Whaanga | 16 h | 0% | 0% | 0% | 0% | 0% | 0% | 25% | 23% | 61% | 25% | 57% | 149% | 119% | 116% | 31% | 100% | 50% | 25% | 31% | 68% |
| Fabrication 8 on the tools · Dave Kemsley | 64 h | 0% | 0% | 0% | 0% | 0% | 0% | 60% | 32% | 38% | 49% | 46% | 43% | 82% | 122% | 162% | 136% | 137% | 147% | 135% | 89% |
| Machining 2 on the tools · Ivan Petrovic | 16 h | 0% | 0% | 0% | 0% | 0% | 0% | 16% | 171% | 38% | 31% | 36% | 96% | 28% | 16% | 16% | 108% | 136% | 56% | 88% | 180% |
| Paint 3 on the tools · Manu Tipene | 24 h | 8% | 8% | 0% | 0% | 0% | 0% | 22% | 75% | 138% | 40% | 46% | 48% | 95% | 74% | 35% | 29% | 130% | 171% | 87% | 97% |
| Hydraulics 4 on the tools · Shaun Corry | 32 h | 5% | 5% | 5% | 5% | 12% | 26% | 195% | 59% | 35% | 62% | 39% | 27% | 59% | 89% | 84% | 75% | 56% | 88% | 119% | 132% |
| Final Assembly 5 on the tools · Tui Fraser | 40 h | 10% | 40% | 45% | 30% | 15% | 15% | 72% | 91% | 90% | 64% | 49% | 78% | 102% | 91% | 46% | 55% | 88% | 111% | 86% | 46% |
| Test Rig 1 on the tools · Barry Mellsop | 8 h | 0% | 19% | 50% | 75% | 25% | 25% | 25% | 81% | 69% | 75% | 25% | 50% | 75% | 94% | 50% | 25% | 69% | 75% | 100% | 44% |
| QC 1 on the tools · Yvonne Tapsell | 8 h | 19% | 0% | 13% | 38% | 56% | 19% | 19% | 19% | 63% | 50% | 56% | 19% | 38% | 56% | 69% | 38% | 19% | 50% | 56% | 75% |