Production Calendar

24 Sep 2026 · 1 machines in view · capacity 14 a week
NB Nathan General Manager
← Today → 24 Sep 2026
Clear
On track At risk Blocked or late Complete Platform

Thu 24 Sep 2026

1 machines onto the bench

Capacity

Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward.
Station Available T 24 Sep
Cutting
2 on the tools · Rangi Whaanga
16 h 31%
Fabrication
8 on the tools · Dave Kemsley
64 h 135%
Machining
2 on the tools · Ivan Petrovic
16 h 88%
Paint
3 on the tools · Manu Tipene
24 h 87%
Hydraulics
4 on the tools · Shaun Corry
32 h 119%
Final Assembly
5 on the tools · Tui Fraser
40 h 86%
Test Rig
1 on the tools · Barry Mellsop
8 h 100%
QC
1 on the tools · Yvonne Tapsell
8 h 56%