Production Calendar

5 Feb 2024 to 5 Apr 2024 · 0 machines in view · capacity 14 a week
NB Nathan General Manager
← Today → 5 Feb 2024 to 5 Apr 2024
Stages Released to production Cutting Fabrication Machining Paint Hydraulics Final Assembly Test Rig QC Ready for despatch where it is now slip past the booked date Platform
Machine
w/c 5 Feb
w/c 12 Feb
w/c 19 Feb
w/c 26 Feb
w/c 4 Mar
w/c 11 Mar
w/c 18 Mar
w/c 25 Mar
w/c 1 Apr
M
5
T
6
W
7
T
8
F
9
M
12
T
13
W
14
T
15
F
16
M
19
T
20
W
21
T
22
F
23
M
26
T
27
W
28
T
29
F
1
M
4
T
5
W
6
T
7
F
8
M
11
T
12
W
13
T
14
F
15
M
18
T
19
W
20
T
21
F
22
M
25
T
26
W
27
T
28
F
29
M
1
T
2
W
3
T
4
F
5
Nothing matches.
Clear the filters to see the whole plan.

Capacity

Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward.