Production Calendar

27 Feb 2023 to 7 Apr 2023 · 0 machines in view · capacity 14 a week
NB Nathan General Manager
← Today → 27 Feb 2023 to 7 Apr 2023
Stages Released to production Cutting Fabrication Machining Paint Hydraulics Final Assembly Test Rig QC Ready for despatch where it is now slip past the booked date Platform
Machine
w/c 27 Feb
w/c 6 Mar
w/c 13 Mar
w/c 20 Mar
w/c 27 Mar
w/c 3 Apr
M
27
T
28
W
1
T
2
F
3
M
6
T
7
W
8
T
9
F
10
M
13
T
14
W
15
T
16
F
17
M
20
T
21
W
22
T
23
F
24
M
27
T
28
W
29
T
30
F
31
M
3
T
4
W
5
T
6
F
7
Nothing matches.
Clear the filters to see the whole plan.

Capacity

Platform
Bench hours loaded against hours available. Anything over 100% cannot be done that day. Days already past are dimmed; the band looks forward.