BO-26-4123

FencePro Farmtek / Sidemount SM1000 for Central Otago Ag Ltd
NB Nathan General Manager
FencePro Farmtek / SM1000 On track
Sales orderSO-26-1222 line 1
Serialassigned at QC sign-off
MastFarmtek
BaseSidemount SM1000
AttachmentsNone
Released12 Aug 2026
Final assembly8 Sep 2026
Promised to dealer15 Sep 2026
Convergence date
7 Sep 2026

Every sub-assembly is ready on or before 8 Sep 2026, the day final assembly is scheduled to start. This machine can be built on its date.

Critical path
Valve bank assembly, Walvoil SD5 4-bank
Complete 7 Sep
Onto the assembly bench 8 Sep 2026
Calculated completion 21 Sep 2026
Promised to dealer 15 Sep 2026

Production stages

Currently at stage 7 of 10 since 8 Sep 2026
  1. Released to production
    12 Aug
  2. Steel cut and prep
    13 Aug
  3. Fabrication and weld
    14 Aug
  4. Machining
    25 Aug
  5. Blast and paint
    28 Aug
  6. Hydraulic assembly
    2 Sep
  7. Final assembly
    8 Sep
  8. Test rig
    10 Sep
  9. QC sign-off
    14 Sep
  10. Ready for despatch
    16 Sep

Sub-assemblies

Platform
7 of 7 complete and in stores
Sub-assembly State Where Hours Required by Ready Verdict
Farmtek mast weldment
Mast weldment · 5 day build · SA-MW-FARMTEK
In stores Stores 13.5 / 13.5 7 Sep 4 Sep Complete 4 Sep
Sidemount SM1000 base weldment
Base weldment · 4 day build · SA-BW-SM1000
In stores Stores 13.4 / 13.4 7 Sep 4 Sep Complete 4 Sep
Hydraulic pack, standard
Hydraulic pack · 2 day build · SA-HP-STD
In stores Stores 2.5 / 2.5 7 Sep 4 Sep Complete 4 Sep
Valve bank assembly, Walvoil SD5 4-bank
Valve bank · 1 day build · SA-VB-SD5-4
In stores Stores 1.2 / 1.2 7 Sep 7 Sep Complete 7 Sep
Ram set, small mast
Ram set · 1 day build · SA-RS-S
In stores Stores 1 / 1 7 Sep 3 Sep Complete 3 Sep
Hose kit, small mast
Hose kit · 1 day build · SA-HK-S
In stores Stores 1.2 / 1.2 7 Sep 2 Sep Complete 2 Sep
Decal and document set, FP
Decal set · 1 day build · SA-DS-FP
In stores Stores 0.5 / 0.5 7 Sep 7 Sep Complete 7 Sep

Value in this job

Standard cost
Material issued to date
$10,003
Labour booked to date
$1,831
Work in progress
$11,834
Material at standard, complete
$10,003
Labour at standard, complete
$2,544
Hours booked
39.8 / 55.3
Sold for
$16,536

HARMONiQ costing and stock valuation come from HARMONiQ.

Activity and correspondence

Component requirements

StockNetting
0 lines still to issue against this machine
Component For Required On hand Allocated ahead Available On order ETA Shortfall