Farmtek / SM1000 On track CustomerCentral Otago Ag Ltd
Serialassigned at QC sign-off
MastFarmtek
BaseSidemount SM1000
AttachmentsNone
Released12 Aug 2026
Final assembly8 Sep 2026
Promised to dealer15 Sep 2026
Convergence date
7 Sep 2026
Every sub-assembly is ready on or before 8 Sep 2026, the day final assembly is scheduled to start. This machine can be built on its date.
Critical path
Valve bank assembly, Walvoil SD5 4-bank
Complete 7 Sep
Onto the assembly bench 8 Sep 2026
Calculated completion 21 Sep 2026
Promised to dealer 15 Sep 2026
Production stages
Currently at stage 7 of 10 since 8 Sep 2026
- Released to production12 Aug
- Steel cut and prep13 Aug
- Fabrication and weld14 Aug
- Machining25 Aug
- Blast and paint28 Aug
- Hydraulic assembly2 Sep
- Final assembly8 Sep
- Test rig10 Sep
- QC sign-off14 Sep
- Ready for despatch16 Sep
Sub-assemblies
Platform
7 of 7 complete and in stores | Sub-assembly | State | Where | Hours | Required by | Ready | Verdict |
|---|---|---|---|---|---|---|
| Farmtek mast weldment Mast weldment · 5 day build · SA-MW-FARMTEK | In stores | Stores | 13.5 / 13.5 | 7 Sep | 4 Sep | Complete 4 Sep |
| Sidemount SM1000 base weldment Base weldment · 4 day build · SA-BW-SM1000 | In stores | Stores | 13.4 / 13.4 | 7 Sep | 4 Sep | Complete 4 Sep |
| Hydraulic pack, standard Hydraulic pack · 2 day build · SA-HP-STD | In stores | Stores | 2.5 / 2.5 | 7 Sep | 4 Sep | Complete 4 Sep |
| Valve bank assembly, Walvoil SD5 4-bank Valve bank · 1 day build · SA-VB-SD5-4 | In stores | Stores | 1.2 / 1.2 | 7 Sep | 7 Sep | Complete 7 Sep |
| Ram set, small mast Ram set · 1 day build · SA-RS-S | In stores | Stores | 1 / 1 | 7 Sep | 3 Sep | Complete 3 Sep |
| Hose kit, small mast Hose kit · 1 day build · SA-HK-S | In stores | Stores | 1.2 / 1.2 | 7 Sep | 2 Sep | Complete 2 Sep |
| Decal and document set, FP Decal set · 1 day build · SA-DS-FP | In stores | Stores | 0.5 / 0.5 | 7 Sep | 7 Sep | Complete 7 Sep |
Value in this job
Standard cost
- Material issued to date
- $10,003
- Labour booked to date
- $1,831
- Work in progress
- $11,834
- Material at standard, complete
- $10,003
- Labour at standard, complete
- $2,544
- Hours booked
- 39.8 / 55.3
- Sold for
- $16,536
HARMONiQ costing and stock valuation come from HARMONiQ.
Activity and correspondence
Component requirements
StockNetting
0 lines still to issue against this machine | Component | For | Required | On hand | Allocated ahead | Available | On order | ETA | Shortfall |
|---|