BO-26-4122

Aitchison Grassfarmer 3113C Trailed HD for Riverina Machinery Pty Ltd
NB Nathan General Manager
Aitchison Grassfarmer 3113C / 1800L / Trailed HD On track
Sales orderSO-26-1220 line 1
Serialassigned at QC sign-off
AttachmentsNone
Released17 Aug 2026
Final assembly8 Sep 2026
Promised to dealer15 Sep 2026
Convergence date
7 Sep 2026

Every sub-assembly is ready on or before 8 Sep 2026, the day final assembly is scheduled to start. This machine can be built on its date.

Critical path
Aitchison 3113 drill frame weldment
Complete 7 Sep
Onto the assembly bench 8 Sep 2026
Calculated completion 16 Sep 2026
Promised to dealer 15 Sep 2026

Production stages

Currently at stage 7 of 10 since 8 Sep 2026
  1. Released to production
    17 Aug
  2. Steel cut and prep
    18 Aug
  3. Fabrication and weld
    19 Aug
  4. Machining
    1 Sep
  5. Blast and paint
    2 Sep
  6. Hydraulic assembly
    4 Sep
  7. Final assembly
    8 Sep
  8. Test rig
    10 Sep
  9. QC sign-off
    11 Sep
  10. Ready for despatch
    14 Sep

Sub-assemblies

Platform
5 of 5 complete and in stores
Sub-assembly State Where Hours Required by Ready Verdict
Aitchison 3113 drill frame weldment
Frame weldment · 8 day build · SA-FW-AI3113
In stores Stores 26.5 / 26.5 7 Sep 7 Sep Complete 7 Sep
Aitchison 1800L seed box
Seed box · 5 day build · SA-SB-AI1800
In stores Stores 9.5 / 9.5 7 Sep 3 Sep Complete 3 Sep
Aitchison inverted-T coulter bank
Coulter bank · 3 day build · SA-CB-AI
In stores Stores 9 / 9 7 Sep 3 Sep Complete 3 Sep
Hydraulic pack, standard
Hydraulic pack · 2 day build · SA-HP-STD
In stores Stores 2.5 / 2.5 7 Sep 3 Sep Complete 3 Sep
Decal and document set, AI
Decal set · 1 day build · SA-DS-AI
In stores Stores 0.5 / 0.5 7 Sep 7 Sep Complete 7 Sep

Value in this job

Standard cost
Material issued to date
$18,585
Labour booked to date
$2,622
Work in progress
$21,207
Material at standard, complete
$18,585
Labour at standard, complete
$3,565
Hours booked
57 / 77.5
Sold for
A$32,120

HARMONiQ costing and stock valuation come from HARMONiQ.

Activity and correspondence

Component requirements

StockNetting
0 lines still to issue against this machine
Component For Required On hand Allocated ahead Available On order ETA Shortfall