Series 4 / SM1000 On track CustomerAGTEC Machinery Ltd
Serialassigned at QC sign-off
MastKHS4
BaseSidemount SM1000
AttachmentsNone
Released4 Aug 2026
Final assembly2 Sep 2026
Promised to dealer9 Sep 2026
Pulled off the bench to get a warranty repair out the door.
Convergence date
1 Sep 2026
Every sub-assembly is ready on or before 2 Sep 2026, the day final assembly is scheduled to start. This machine can be built on its date.
Critical path
Sidemount SM1000 base weldment
Complete 1 Sep
Onto the assembly bench 8 Sep 2026
Calculated completion 21 Sep 2026
Promised to dealer 9 Sep 2026
Production stages
Currently at stage 7 of 10 since 7 Sep 2026
- Released to production4 Aug
- Steel cut and prep5 Aug
- Fabrication and weld6 Aug
- Machining18 Aug
- Blast and paint21 Aug
- Hydraulic assembly27 Aug
- Final assembly2 Sep
- Test rig4 Sep
- QC sign-off8 Sep
- Ready for despatch10 Sep
Sub-assemblies
Platform
7 of 7 complete and in stores | Sub-assembly | State | Where | Hours | Required by | Ready | Verdict |
|---|---|---|---|---|---|---|
| Kinghitter Series 4 mast weldment Mast weldment · 9 day build · SA-MW-KHS4 | In stores | Stores | 23.3 / 23.3 | 1 Sep | 27 Aug | Complete 27 Aug |
| Sidemount SM1000 base weldment Base weldment · 4 day build · SA-BW-SM1000 | In stores | Stores | 13.4 / 13.4 | 1 Sep | 1 Sep | Complete 1 Sep |
| Hydraulic pack, standard Hydraulic pack · 2 day build · SA-HP-STD | In stores | Stores | 2.5 / 2.5 | 1 Sep | 27 Aug | Complete 27 Aug |
| Valve bank assembly, Walvoil SD5 6-bank Valve bank · 1 day build · SA-VB-SD5-6 | In stores | Stores | 1.5 / 1.5 | 1 Sep | 27 Aug | Complete 27 Aug |
| Ram set, large mast Ram set · 1 day build · SA-RS-L | In stores | Stores | 1.5 / 1.5 | 1 Sep | 1 Sep | Complete 1 Sep |
| Hose kit, large mast Hose kit · 1 day build · SA-HK-L | In stores | Stores | 2 / 2 | 1 Sep | 31 Aug | Complete 31 Aug |
| Decal and document set, KH Decal set · 1 day build · SA-DS-KH | In stores | Stores | 0.5 / 0.5 | 1 Sep | 28 Aug | Complete 28 Aug |
Value in this job
Standard cost
- Material issued to date
- $11,702
- Labour booked to date
- $2,355
- Work in progress
- $14,057
- Material at standard, complete
- $11,702
- Labour at standard, complete
- $3,068
- Hours booked
- 51.2 / 66.7
- Sold for
- $28,575
HARMONiQ costing and stock valuation come from HARMONiQ.
Activity and correspondence
Component requirements
StockNetting
0 lines still to issue against this machine | Component | For | Required | On hand | Allocated ahead | Available | On order | ETA | Shortfall |
|---|