BO-26-4119

Kinghitter Series 4 / Sidemount SM1000 for AGTEC Machinery Ltd
NB Nathan General Manager
Kinghitter Series 4 / SM1000 On track
Sales orderSO-26-1211 line 1
Serialassigned at QC sign-off
MastKHS4
BaseSidemount SM1000
AttachmentsNone
Released4 Aug 2026
Final assembly2 Sep 2026
Promised to dealer9 Sep 2026

Pulled off the bench to get a warranty repair out the door.

Convergence date
1 Sep 2026

Every sub-assembly is ready on or before 2 Sep 2026, the day final assembly is scheduled to start. This machine can be built on its date.

Critical path
Sidemount SM1000 base weldment
Complete 1 Sep
Onto the assembly bench 8 Sep 2026
Calculated completion 21 Sep 2026
Promised to dealer 9 Sep 2026

Production stages

Currently at stage 7 of 10 since 7 Sep 2026
  1. Released to production
    4 Aug
  2. Steel cut and prep
    5 Aug
  3. Fabrication and weld
    6 Aug
  4. Machining
    18 Aug
  5. Blast and paint
    21 Aug
  6. Hydraulic assembly
    27 Aug
  7. Final assembly
    2 Sep
  8. Test rig
    4 Sep
  9. QC sign-off
    8 Sep
  10. Ready for despatch
    10 Sep

Sub-assemblies

Platform
7 of 7 complete and in stores
Sub-assembly State Where Hours Required by Ready Verdict
Kinghitter Series 4 mast weldment
Mast weldment · 9 day build · SA-MW-KHS4
In stores Stores 23.3 / 23.3 1 Sep 27 Aug Complete 27 Aug
Sidemount SM1000 base weldment
Base weldment · 4 day build · SA-BW-SM1000
In stores Stores 13.4 / 13.4 1 Sep 1 Sep Complete 1 Sep
Hydraulic pack, standard
Hydraulic pack · 2 day build · SA-HP-STD
In stores Stores 2.5 / 2.5 1 Sep 27 Aug Complete 27 Aug
Valve bank assembly, Walvoil SD5 6-bank
Valve bank · 1 day build · SA-VB-SD5-6
In stores Stores 1.5 / 1.5 1 Sep 27 Aug Complete 27 Aug
Ram set, large mast
Ram set · 1 day build · SA-RS-L
In stores Stores 1.5 / 1.5 1 Sep 1 Sep Complete 1 Sep
Hose kit, large mast
Hose kit · 1 day build · SA-HK-L
In stores Stores 2 / 2 1 Sep 31 Aug Complete 31 Aug
Decal and document set, KH
Decal set · 1 day build · SA-DS-KH
In stores Stores 0.5 / 0.5 1 Sep 28 Aug Complete 28 Aug

Value in this job

Standard cost
Material issued to date
$11,702
Labour booked to date
$2,355
Work in progress
$14,057
Material at standard, complete
$11,702
Labour at standard, complete
$3,068
Hours booked
51.2 / 66.7
Sold for
$28,575

HARMONiQ costing and stock valuation come from HARMONiQ.

Activity and correspondence

Component requirements

StockNetting
0 lines still to issue against this machine
Component For Required On hand Allocated ahead Available On order ETA Shortfall