BO-26-4109

FencePro Ultra G4 / Sidemount SM420 for Webbline Agriculture Ltd
NB Nathan General Manager
FencePro Ultra G4 / SM420 On track
Sales orderSO-26-1195 line 1
Serialassigned at QC sign-off
MastUltra G4
BaseSidemount SM420
AttachmentsNone
Released29 Jul 2026
Final assembly24 Aug 2026
Promised to dealer31 Aug 2026

Machining queue. The line boring on the pin bosses is one machine deep.

Convergence date
21 Aug 2026

Every sub-assembly is ready on or before 24 Aug 2026, the day final assembly is scheduled to start. This machine can be built on its date.

Critical path
Sidemount SM420 base weldment
Complete 21 Aug
Onto the assembly bench 8 Sep 2026
Calculated completion 18 Sep 2026
Promised to dealer 31 Aug 2026

Production stages

Currently at stage 8 of 10 since 2 Sep 2026
  1. Released to production
    29 Jul
  2. Steel cut and prep
    30 Jul
  3. Fabrication and weld
    31 Jul
  4. Machining
    11 Aug
  5. Blast and paint
    12 Aug
  6. Hydraulic assembly
    17 Aug
  7. Final assembly
    24 Aug
  8. Test rig
    27 Aug
  9. QC sign-off
    28 Aug
  10. Ready for despatch
    31 Aug

Sub-assemblies

Platform
7 of 7 complete and in stores
Sub-assembly State Where Hours Required by Ready Verdict
Ultra G4 mast weldment
Mast weldment · 9 day build · SA-MW-ULTRAG4
In stores Stores 23 / 23 21 Aug 20 Aug Complete 20 Aug
Sidemount SM420 base weldment
Base weldment · 3 day build · SA-BW-SM420
In stores Stores 9 / 9 21 Aug 21 Aug Complete 21 Aug
Hydraulic pack, ActiveBlock
Hydraulic pack · 2 day build · SA-HP-AB
In stores Stores 3 / 3 21 Aug 20 Aug Complete 20 Aug
Valve bank assembly, Walvoil ActiveBlock
Valve bank · 1 day build · SA-VB-AB
In stores Stores 2 / 2 21 Aug 21 Aug Complete 21 Aug
Ram set, large mast
Ram set · 1 day build · SA-RS-L
In stores Stores 1.5 / 1.5 21 Aug 19 Aug Complete 19 Aug
Hose kit, large mast
Hose kit · 1 day build · SA-HK-L
In stores Stores 2 / 2 21 Aug 18 Aug Complete 18 Aug
Decal and document set, FP
Decal set · 1 day build · SA-DS-FP
In stores Stores 0.5 / 0.5 21 Aug 18 Aug Complete 18 Aug

Value in this job

Standard cost
Material issued to date
$12,643
Labour booked to date
$2,737
Work in progress
$15,380
Material at standard, complete
$12,643
Labour at standard, complete
$2,898
Hours booked
59.5 / 63
Sold for
$25,900

HARMONiQ costing and stock valuation come from HARMONiQ.

Activity and correspondence

Component requirements

StockNetting
0 lines still to issue against this machine
Component For Required On hand Allocated ahead Available On order ETA Shortfall