Mule / RB800 Complete CustomerTaranaki Fencing Contractors Ltd
SerialFP26-4826
MastMule
BaseRB800
AttachmentsNone
Released6 Aug 2026
Final assembly27 Aug 2026
Promised to dealer3 Sep 2026
Convergence date
26 Aug 2026
Every sub-assembly is ready on or before 27 Aug 2026, the day final assembly is scheduled to start. This machine can be built on its date.
Critical path
RB800 base weldment
Complete 26 Aug
Onto the assembly bench 27 Aug 2026
Calculated completion 2 Sep 2026
Promised to dealer 3 Sep 2026
Production stages
Currently at stage 10 of 10 since 2 Sep 2026
- Released to production6 Aug
- Steel cut and prep7 Aug
- Fabrication and weld10 Aug
- Machining18 Aug
- Blast and paint19 Aug
- Hydraulic assembly21 Aug
- Final assembly27 Aug
- Test rig31 Aug
- QC sign-off1 Sep
- Ready for despatch2 Sep
Sub-assemblies
Platform
7 of 7 complete and in stores | Sub-assembly | State | Where | Hours | Required by | Ready | Verdict |
|---|---|---|---|---|---|---|
| Mule mast weldment Mast weldment · 6 day build · SA-MW-MULE | In stores | Stores | 17.7 / 17.7 | 26 Aug | 21 Aug | Complete 21 Aug |
| RB800 base weldment Base weldment · 6 day build · SA-BW-RB800 | In stores | Stores | 19.2 / 19.2 | 26 Aug | 26 Aug | Complete 26 Aug |
| Hydraulic pack, standard Hydraulic pack · 2 day build · SA-HP-STD | In stores | Stores | 2.5 / 2.5 | 26 Aug | 21 Aug | Complete 21 Aug |
| Valve bank assembly, Walvoil SD5 6-bank Valve bank · 1 day build · SA-VB-SD5-6 | In stores | Stores | 1.5 / 1.5 | 26 Aug | 24 Aug | Complete 24 Aug |
| Ram set, medium mast Ram set · 1 day build · SA-RS-M | In stores | Stores | 1.2 / 1.2 | 26 Aug | 21 Aug | Complete 21 Aug |
| Hose kit, medium mast Hose kit · 1 day build · SA-HK-M | In stores | Stores | 1.5 / 1.5 | 26 Aug | 21 Aug | Complete 21 Aug |
| Decal and document set, FP Decal set · 1 day build · SA-DS-FP | In stores | Stores | 0.5 / 0.5 | 26 Aug | 24 Aug | Complete 24 Aug |
Value in this job
Standard cost
- Material issued to date
- $13,148
- Labour booked to date
- $3,041
- Work in progress
- $16,188
- Material at standard, complete
- $13,148
- Labour at standard, complete
- $3,041
- Hours booked
- 66.1 / 66.1
- Sold for
- $28,440
HARMONiQ costing and stock valuation come from HARMONiQ.
Activity and correspondence
Component requirements
StockNetting
0 lines still to issue against this machine | Component | For | Required | On hand | Allocated ahead | Available | On order | ETA | Shortfall |
|---|