BO-26-4104

FencePro Mule / PB650 for NC Equipment Ltd
NB Nathan General Manager
FencePro Mule / PB650 Complete
Sales orderSO-26-1188 line 1
SerialFP26-4824
MastMule
BasePB650
AttachmentsNone
Released6 Aug 2026
Final assembly26 Aug 2026
Promised to dealer2 Sep 2026
Convergence date
25 Aug 2026

Every sub-assembly is ready on or before 26 Aug 2026, the day final assembly is scheduled to start. This machine can be built on its date.

Critical path
Valve bank assembly, Walvoil SD5 6-bank
Complete 25 Aug
Onto the assembly bench 26 Aug 2026
Calculated completion 3 Sep 2026
Promised to dealer 2 Sep 2026

Production stages

Currently at stage 10 of 10 since 1 Sep 2026
  1. Released to production
    6 Aug
  2. Steel cut and prep
    7 Aug
  3. Fabrication and weld
    10 Aug
  4. Machining
    18 Aug
  5. Blast and paint
    19 Aug
  6. Hydraulic assembly
    24 Aug
  7. Final assembly
    26 Aug
  8. Test rig
    28 Aug
  9. QC sign-off
    31 Aug
  10. Ready for despatch
    1 Sep

Sub-assemblies

Platform
7 of 7 complete and in stores
Sub-assembly State Where Hours Required by Ready Verdict
Mule mast weldment
Mast weldment · 6 day build · SA-MW-MULE
In stores Stores 17.7 / 17.7 25 Aug 21 Aug Complete 21 Aug
PB650 base weldment
Base weldment · 5 day build · SA-BW-PB650
In stores Stores 16.1 / 16.1 25 Aug 21 Aug Complete 21 Aug
Hydraulic pack, standard
Hydraulic pack · 2 day build · SA-HP-STD
In stores Stores 2.5 / 2.5 25 Aug 24 Aug Complete 24 Aug
Valve bank assembly, Walvoil SD5 6-bank
Valve bank · 1 day build · SA-VB-SD5-6
In stores Stores 1.5 / 1.5 25 Aug 25 Aug Complete 25 Aug
Ram set, medium mast
Ram set · 1 day build · SA-RS-M
In stores Stores 1.2 / 1.2 25 Aug 25 Aug Complete 25 Aug
Hose kit, medium mast
Hose kit · 1 day build · SA-HK-M
In stores Stores 1.5 / 1.5 25 Aug 21 Aug Complete 21 Aug
Decal and document set, FP
Decal set · 1 day build · SA-DS-FP
In stores Stores 0.5 / 0.5 25 Aug 24 Aug Complete 24 Aug

Value in this job

Standard cost
Material issued to date
$12,586
Labour booked to date
$2,898
Work in progress
$15,484
Material at standard, complete
$12,586
Labour at standard, complete
$2,898
Hours booked
63 / 63
Sold for
$20,659

HARMONiQ costing and stock valuation come from HARMONiQ.

Activity and correspondence

Component requirements

StockNetting
0 lines still to issue against this machine
Component For Required On hand Allocated ahead Available On order ETA Shortfall