BO-26-4102

Maxam Rotary Mower 1800 Mounted for Agricentre South Ltd
NB Nathan General Manager
Maxam Rotary Mower 1800 / Mounted Complete
Sales orderSO-26-1183 line 1
SerialMX26-4822
AttachmentsNone
Released5 Aug 2026
Final assembly25 Aug 2026
Promised to dealer1 Sep 2026
Convergence date
24 Aug 2026

Every sub-assembly is ready on or before 25 Aug 2026, the day final assembly is scheduled to start. This machine can be built on its date.

Critical path
Maxam 1800 deck weldment
Complete 24 Aug
Onto the assembly bench 25 Aug 2026
Calculated completion 3 Sep 2026
Promised to dealer 1 Sep 2026

Production stages

Currently at stage 10 of 10 since 31 Aug 2026
  1. Released to production
    5 Aug
  2. Steel cut and prep
    6 Aug
  3. Fabrication and weld
    7 Aug
  4. Machining
    13 Aug
  5. Blast and paint
    18 Aug
  6. Hydraulic assembly
    24 Aug
  7. Final assembly
    25 Aug
  8. Test rig
    26 Aug
  9. QC sign-off
    27 Aug
  10. Ready for despatch
    31 Aug

Sub-assemblies

Platform
4 of 4 complete and in stores
Sub-assembly State Where Hours Required by Ready Verdict
Maxam 1800 deck weldment
Deck weldment · 4 day build · SA-DW-MX1800
In stores Stores 14.5 / 14.5 24 Aug 24 Aug Complete 24 Aug
Maxam 1800 drive pack
Drive pack · 2 day build · SA-DP-MX1800
In stores Stores 3 / 3 24 Aug 24 Aug Complete 24 Aug
Maxam 1800 rotor assembly
Rotor assembly · 2 day build · SA-RA-MX1800
In stores Stores 4.5 / 4.5 24 Aug 24 Aug Complete 24 Aug
Decal and document set, MX
Decal set · 1 day build · SA-DS-MX
In stores Stores 0.5 / 0.5 24 Aug 20 Aug Complete 20 Aug

Value in this job

Standard cost
Material issued to date
$6,815
Labour booked to date
$1,725
Work in progress
$8,540
Material at standard, complete
$6,815
Labour at standard, complete
$1,725
Hours booked
37.5 / 37.5
Sold for
$11,544

HARMONiQ costing and stock valuation come from HARMONiQ.

Activity and correspondence

Component requirements

StockNetting
0 lines still to issue against this machine
Component For Required On hand Allocated ahead Available On order ETA Shortfall